26. Buckeye Company has provided the following data for maintenance cost: Prior Year Current Year Machine hours…………………………….. 12,500 15,000 Maintenance cost………………………….. $27,000 $31,000 The best...






26. Buckeye Company has provided the following data for maintenance cost:
Prior Year

Current Year
Machine hours……………………………..


12,500

15,000
Maintenance cost…………………………..

$27,000

$31,000
The best estimate of the cost formula for maintenance would be:
A. $7,000 per year plus $1.60 per machine hour
B. $27,000 per year plus $1.60 per machine hour
C. $21,625 per year plus $0.625 per machine hour
D. $7,000 per year plus $0.625 per machine hour