Case Study: Housing NSW Housing NSW is an agency of the Department of Family and Community Services that is responsible for the provision and management of public housing services with the aim to...

1 answer below »

Case Study: Housing NSW


Housing NSW is an agency of the Department of Family and Community Services that is responsible for the provision and management of public housing services with the aim to prevent homelessness in the state of New South Wales, Australia. Housing NSW provides a range of services including public and community housing, housing for people of Aboriginal and Torres Strait Islander backgrounds, support services for people with special needs linked to government and non-government agencies, private rental assistance and subsidies, advice and assistance for home-buyers, the development of affordable housing, community regeneration, and development and regulation of social housing policies.


“Our vision is a simple client experience, where modern technology and straightforward processes empower staff to deliver great client service and enable clients to choose how they interact with us and manage their own information”.


Imagine that you are the system analyst in the initial stages of the project. The projects aim is to build a system ‘MyHousing’ that will allow clients to submit applications online, clients can apply for housing assistance or make a change to their application, quickly and easily. This service is available 24/7. It enables clients to upload supporting documents and confirm identity and income information online. Client application forms are then integrated automatically into back end systems, significantly reducing administrative tasks.


Note: This is a real project, so there will be many sources of information available for you to research. This MyHousing project is actually complete and in use, however, when you are completing this assessment and writing the vision document assume the project is in the early stages and the system has not yet been built.






Further Background






Refer to background information provided in Assessments 1 and 2 regarding MyHousing project.






Complete the Following






Please refer to the marking guide when preparing your response to see what criteria and standards will be used to assess your work and your progress.






Agile Methodologies






Compare and contrast Unified Process (UP) and Scrum. Then recommend either Unified Process or Scrum you will use for the proposed system and briefly describe why.






Plan and Monitor Project






Planning and monitoring project activities are important part of system development. Review all possible system functions that you identifed in assignment 1 and 2, and complete the following tasks. You are not required to explain these tasks, just draw a table for each task with some relevant paramters. Please note, as this is not a complete project, if information is not given you should assume reasonably.



  • Estimate the development cost and the time required to complete MyHousing project.

  • Develop a work breakdown structure (WBS) for the MyHousing project’s first iteration.

  • Prepare a detailed work schedule for the first iteration.


RATIONALE



This assessment task will assess the following learning outcome/s:



  • be able to evaluate development requirements and prepare a feasibility proposal based on multi-disciplinary (financial, human resource, technological) analyses.

  • be able to formulate and justify system requirement models based on evaluation of given situations.

  • be able to assemble the components of a requirements model using the tools and techniques of object oriented or structured systems modelling.

Answered Same DayMay 24, 2021

Answer To: Case Study: Housing NSW Housing NSW is an agency of the Department of Family and Community Services...

Kshitij answered on May 29 2021
135 Votes
New south wales, Australia
Housing project
Student name
Student ID
Contents
Agile methodology    3
Unified process    3
Inception    4
Elaboration    4
Construction    4
Transition    4
Scrum    4
Recommendation    6
Plan and monitor    6
Cost and the time is taken into account for MyHousing    6
Work schedule    7
Reference    9
Table of figures
F
igure 1 unified process model    4
Figure 2 phases of scrum    6
Agile methodology
Unified process
The model of the process us made available to the certainly used case, center of architecture, iterative and various incremental working that makes use of the leverages of the certain UML and is quite compatible with the several engineering and its models which are being taken into account by the processing system in the operations. One of the best benefits which can be attained by making use of the unified system of processing in that particular modeling system is that the same can be put to use for the development of the software system with new ad advancement in the technology sector at the different stages of the system and to the complexity related to the same (Bernard, Zeppelzauer, et.al., 2018). The unified process and its method consist of various extensible frameworks that can be used by the user by customizable requirements.

Figure 1 unified process model
As per the unified process processing model, there are considerably four phases which relate to the development phases of the process undertaken and these phases are stated as follows:
Inception
This is considered to be lease time-consuming stage or phase of the undertaken process, and consist of various objectives or goals such as establishment, generation of the initiate budget relating to the specified project and the related schedule to the same, respective study related to the feasibility of the project and the development of the project.
Elaboration
This phase deals with the gathering or collecting requirement of the phase and all the requested requirements of the project are being summarised in this particular phase. The main objective of the phase is to ascertain the main factors responsible for the risk and for the purpose of making certain verifications to the respective system.
Construction
This phase is considered to be one of the most time-consuming phases in the procedure, the formation of the project is done on the basis of the information gathered in the evaluation and elaboration of the respective project (Kirk, and Walker, 2019). The respective features of the same have been incorporated or implemented in the procedure making use of the series of parts and small iterative tasks based on the deadlines stated which ultimately results in executable outcomes related to the development of the various software.
Transition
This is the last and final phase of the respective model phase which was undertaken, in this particular phase the deployment of the software which was developed has been taken into account and is termed as the destination relating to the target system used by the users. The feedback obtained from such deployment is then put to use for the development and maintenance of the system in the future.
Scrum
Scrum is considered to be the agile method of the respective management and the development related to the...