Complete this exercise in MSProject. Assume a start date of June 1 of the current year and a normal 5-day work week. Submit both your MSProject file and your answers to the questions below.
Consider a project that consists of 8 tasks with predecessors and task estimates as shown:
Task
Predecessor
Duration
A
-
2
B
7
C
4
D
B, C
8
E
F
6
G
3
H
E, F