GSGM7334 Project Management Assignment 1: GADGET TOY COMPANY Kumar, project manager at Gadget Toy Company (Gadget), had just submitted a proposal for funding to the new product review committee. He...

2 answer below »
COPY AND PASTE YOUR ASSIGNMENT HERE


GSGM7334 Project Management Assignment 1: GADGET TOY COMPANY Kumar, project manager at Gadget Toy Company (Gadget), had just submitted a proposal for funding to the new product review committee. He recommended that Gadget introduce, through its retail distribution network, a new children‘s toy based on a popular cartoon character. Kumar felt that if he could get the product out by Christmas, Gadget could take advantage of what he felt would be strong market demand. He estimated that the sales could reach $200,000. However, due to the volatility of the market for these types of games, Kumar could not be certain that the product would have the same level of market acceptance the following year. It was now May 6, 2019, and Kumar knew he would have to manage the timing of the project carefully to meet the delivery date of September 13th , 2019 just 19 weeks away. Gadget‘s head office was in Klang, Selangor, where it also operated a manufacturing plant and distribution center. Whenever possible, Gadget preferred to manufacture its products in-house. Kumar expected feedback from the committee the end of the week, at which time he would begin coordinating the launch of the project. Since Kumar was an experienced project manager, he established a preliminary list of activities, as shown in Exhibit 1. Based on his schedule, Kumar felt he could start work on some activities immediately, such as finalizing the product design and placing an order for the equipment. However, many of the activities had to be performed sequentially. For example, he could not train the workers until the equipment was installed and the tools for the machine were completed. Similarly, he could not order the raw material until the engineering work was complete and the advertising plan was completed, since the advertising plan would influence colour selection. Concerned about the delivery schedule, Kumar investigated opportunities to cut the project time. After talking with the marketing manager, Sheila, Kumar learned that he could reduce product advertising. Sheila anticipated only a small 1% reduction in sales for each week of lost advertising. However, she indicated that Kumar could not get away with less than six weeks of advertising for a new product of this nature. Kumar also spoke with Steven, the production manager at the tool shop. Steven offered to speed up the tool build by working two weekends, for a total cost of $10,000. Steven thought he could improve their delivery time by two weeks if Kumar authorized this extra cost. QUESTIONS: 1. Prepare the network diagram for the above project. How long will it take to complete the project? 2. Establish the ‘float’ or ‘slack’ times for each activity. 3. Based on the information in the case study, evaluate the options Kumar can do to meet the September 15th deadline. What is your recommendation? EXHIBIT 1: ACTIVITIES NEEDED FOR NEW PRODUCT INTRODUCTION Activity Description Immediate Predecessor Estimated Time (weeks) A 1 obtain funding approval __ 1 B 2 finalize engineering A 1 C 3 deliver new equipment A 8 D 4 build dies/tools B 12 E 5 install equipment C 1 F 6 train workers D, E 1 G 7 de-bug process F 1 H 8 establish advertising plan A 1 I 9 finalize package and art work H 2 J 10 advertise H 12 K 11 raw material delivery D, I 2 L 12 initial production run G, K 3 M 13 ship product J, L 1
Answered 5 days AfterJan 19, 2021

Answer To: GSGM7334 Project Management Assignment 1: GADGET TOY COMPANY Kumar, project manager at Gadget Toy...

Amar answered on Jan 25 2021
142 Votes
Gadget Toy Company – Assignment 1
Question 1
On the basis of the schedule in Table 1 and Network Diagram in Figure 1, the project shall be completed on 15th November 2019 based on the initia
l plan.
Figure 1 – Network Diagram
Table 1 – Schedule
    TASK ID
    Task Name
    Duration
    Start
    Finish
    Predecessors
    0
    GADGET TOY COMPANY - NEW PRODUCT INTRODUCTION
    140 days
    Mon 06-05-19 8:00 AM
    Fri 15-11-19 5:00 PM
     
    A - 1
    Obtain funding approvals
    1 Week
    Mon 06-05-19 8:00 AM
    Tue 14-05-19 5:00 PM
     
    B - 2
    Finalise engineering
    1 Week
    Wed 15-05-19 8:00 AM
    Thu 23-05-19 5:00 PM
    A - 1
    C - 3
    Deliver new equipment.
    8 Weeks
    Wed 15-05-19 8:00 AM
    Wed 31-07-19 5:00 PM
    A - 1
    D - 4
    Build dies / Tools
    12 Weeks
    Fri 24-05-19 8:00 AM
    Wed 18-09-19 5:00 PM
    B - 2
    E - 5
    Install equipment
    1 Week
    Thu 01-08-19 8:00 AM
    Fri 09-08-19 5:00 PM
    C - 3
    F - 6
    Train workers
    1 Week
    Thu 19-09-19 8:00 AM
    Fri 27-09-19 5:00 PM
    D - 4, E - 5
    G - 7
    Debug process
    1 Week
    Mon 30-09-19 8:00 AM
    Tue 08-10-19 5:00 PM
    F - 6
    H - 8
    Establish advertising plans
    5 days
    Wed 15-05-19 8:00 AM
    Thu 23-05-19 5:00 PM
    A - 1
    I - 9
    Finalise Package & Art Work
    2 Weeks
    Fri 24-05-19 8:00 AM
    Wed 12-06-19 5:00 PM
    H - 8
    J - 10
    Advertise
    12 Weeks
    Fri 24-05-19 8:00 AM
    Wed 18-09-19 5:00 PM
    H - 8
    K - 11
    Raw Materials Delivery
    2 Weeks
    Thu 19-09-19 8:00 AM
    Tue 08-10-19 5:00 PM
    D - 4, I - 9
    L - 12
    Initial Production Run
    3 Weeks
    Wed 09-10-19 8:00 AM
    Wed 06-11-19 5:00 PM
    G - 7, K - 11
    M - 13
    Ship Product
    1 Week
    Thu 07-11-19 8:00 AM
    Fri 15-11-19 5:00 PM
    J - 10, L - 12
1
Running Header: Gadget Toy Company – Assignment 1
2
Gadget Toy Company – Assignment 1
Question 2
The Table 2 below presents the detailed schedule for the project based on initial planning along with slack as well as float computations.
Table 2...