Create a first draft of a WBS from the following scenario. Make assumptions as neededbased on the section about project planning considerations and constraints in thischapter. In your WBS, describe the skill sets required for the tasks you have planned.Sequential Label and Supply has a problem with employees surfing the Web to
access material the company deems inappropriate for a professional environment. There-fore, SLS wants to insert a filtering device in the company Internet connection that
blocks certain Web locations and content. According to the vendor, the filter is a hard-ware appliance that costs $18,000 and requires 150 hours to install and configure. Tech-nical support for the filter costs 18 percent of the purchase price and includes a training
allowance for the year. A software component that runs on the administrator’s desktop
computer is needed to administer the filter; this component costs $550. A monthly sub-scription provides the list of sites to be blocked and costs $250 per month. An estimated
four hours per week are required for administrative functions.