BUSI 681Proposed Project Model: Project File Assignment InstructionsOverviewPart 1 of your Proposed Project Model presented essential planning elements for your selected project. Part 2 will...

1 answer below »
EXPERT WILL HAVE TO LOG INTO MY COMPUTER WITH ANYDESK TO USE PROJECT EXCEL TO COMPLETE ASSIGNMENT


BUSI 681 Proposed Project Model: Project File Assignment Instructions Overview Part 1 of your Proposed Project Model presented essential planning elements for your selected project. Part 2 will build upon these initial plans, allowing you the opportunity to use project management software to build a task list, create a Gantt Chart, input resources, develop a schedule, and plan for certain particulars that are common on many projects. This aspect of the Case Study will help develop your develop your software skills and provide practical application of the concepts we study. Instructions The following will be submitted in one MS Project document. 1. Open a new project in Microsoft Project. Save the file in this format: LastName_Project_Name 2. Have the entire project as the first task you input (that is, input the name of your project on the first line). Provide some overarching information about your project. In the Notes file, describe the project and list the key deliverables. Include any other information that may be helpful to your project. 3. Establish a project start date. In the Notes section, explain why you selected this date. 4. Create a work breakdown structure (WBS) by decomposing the scope for your project into deliverables and enter these as “tasks” in your project file. You must have at least 5 deliverables. 5. Decompose the deliverables further into work packages (tasks) and enter them under your deliverables. It is helpful to keep your deliverables as nouns, and to use verbs for each task. Include enough detail to have 20–25 unique tasks. 6. Use the “Indent Task” button to create a hierarchy that delineates deliverables and tasks. 7. Code the project following the 1.1, 1.1.1, 1.2 format. 8. Establish the project schedule by estimating time durations for all of your individual tasks. Enter the duration (in days) for each task. 9. Using a task’s Notes feature, justify the time estimates for at least 5 tasks. For example, you might make the following note: “This will take 3 days to allow the paint to dry before applying the trim.” 10. Enter at least 3 milestones for your project. Milestones typically use passive verbs (i.e. Phase 1 completed) and do not have any duration assigned to them (0 days). 11. Link all of your individual tasks and milestones. You can use the “link” button (appears as a chain link) after selecting the 2 tasks to be linked. Note that there are numerous ways to link tasks. Vary your linkages by including at least 2 relationships that are not Microsoft Project’s default (Finish-to-Start) relationships. 12. Not all tasks start immediately after a task ends (they “lag”) or wait until a task is completely finished before starting (they “lead”). Therefore, have at least 1 task include lead time or lag time. In the Notes section for this task, indicate why there would be a lead/lag for that particular task. 13. Next, begin to assign workers and estimate your resource costs. Enter at least 6 human resources on the Resource Sheet. 14. Add comments to at least half of your resources to provide information about those resources. Note things such as why they were selected, potential scheduling issues, a potential back-up, or other information that a project manager might find helpful. 15. In order to determine the budget for your project, you must input your labor costs. After your resources are entered, include wage rates for each individual resource. 16. For every task, assign the appropriate resource(s). Do not assign resources to summary tasks (your deliverables) or milestones (event markers). 17. If Microsoft Project displays a red human resource icon, the associated resource is over-allocated. Determine how best to address the problem and make the needed changes. If a resource can be over-allocated, justify the “why” in the task’s Notes. 18. When tasks, costs, and resources are entered correctly and you have double-checked for accuracy, set the project baseline. This sets the budget and schedule for the project. 19. Next, display the project as a network diagram to show the critical path in your project. 20. Save and submit the document. Note: Your assignment will be checked for originality via the Turnitin plagiarism tool. Page 2 of 2 BUSI 681 Page 1 of 2 P ROPOSED P ROJECT M ODEL : P ROJECT F ILE A SSIGNMENT I NSTRUCTIONS O VERVIEW Part 1 of your Proposed Project Model presented essential planning elements for your selected project. Part 2 will build upon these initial plans, allowing you the opportunity to use project management software to build a task list, create a Gantt Chart, input resources, develop a schedule, a nd plan for certain particulars that are common on many projects. This aspect of the Case Study will help develop your develop your software skills and provide practical application of the concepts we study . I NSTRUCTIONS The following will be submitted in one MS Project document. 1. Open a new project in Microsoft Project. Save the file in this format: LastName_Project_Name 2. Have the entire project as the first task you input (that is, input the name of your project on the fi rst line). Provide some overarching information about your project. In the Notes file, describe the project and list the key deliverables. Include any other information that may be helpful to your project. 3. Establish a project start date. In the Notes secti on, explain why you selected this date. 4. Create a work breakdown structure (WBS) by decomposing the scope for your project into deliverables and enter these as “tasks” in your project file. You must have at least 5 deliverables. 5. Decompose the deliverables f urther into work packages (tasks) and enter them under your deliverables. It is helpful to keep your deliverables as nouns, and to use verbs for each task. Include enough detail to have 20 – 25 unique tasks. 6. Use the “Indent Task” button to create a hierarchy that delineates deliverables and tasks. 7. Code the project following the 1.1, 1.1.1, 1.2 format. 8. Establish the project schedule by estimating time durations for all of your individual tasks. Enter the duration (in days) for each task. 9. Using a task’s Notes f eature, justify the time estimates for at least 5 tasks. For example, you might make the following note: “This will take 3 days to allow the paint to dry before applying the trim.” 10. Enter at least 3 milestones for your project. Milestones typically use pass ive verbs (i.e. Phase 1 completed) and do not have any duration assigned to them (0 days). 11. Link all of your individual tasks and milestones. You can use the “link” button (appears as a chain link) after selecting the 2 tasks to be linked. Note that there a re numerous ways to link tasks. Vary your linkages by including at least 2 relationships that are not Microsoft Project’s default (Finish - to - Start) relationships. 12. Not all tasks start immediately after a task ends (they “lag”) or wait until a task is comple tely finished before starting (they “lead”). Therefore, have at least 1 task include lead time or lag time. In the Notes section for this task, indicate why there would be a lead/lag for that particular task. BUSI 681 Page 1 of 2 PROPOSED PROJECT MODEL: PROJECT FILE ASSIGNMENT INSTRUCTIONS OVERVIEW Part 1 of your Proposed Project Model presented essential planning elements for your selected project. Part 2 will build upon these initial plans, allowing you the opportunity to use project management software to build a task list, create a Gantt Chart, input resources, develop a schedule, and plan for certain particulars that are common on many projects. This aspect of the Case Study will help develop your develop your software skills and provide practical application of the concepts we study. INSTRUCTIONS The following will be submitted in one MS Project document. 1. Open a new project in Microsoft Project. Save the file in this format: LastName_Project_Name 2. Have the entire project as the first task you input (that is, input the name of your project on the first line). Provide some overarching information about your project. In the Notes file, describe the project and list the key deliverables. Include any other information that may be helpful to your project. 3. Establish a project start date. In the Notes section, explain why you selected this date. 4. Create a work breakdown structure (WBS) by decomposing the scope for your project into deliverables and enter these as “tasks” in your project file. You must have at least 5 deliverables. 5. Decompose the deliverables further into work packages (tasks) and enter them under your deliverables. It is helpful to keep your deliverables as nouns, and to use verbs for each task. Include enough detail to have 20–25 unique tasks. 6. Use the “Indent Task” button to create a hierarchy that delineates deliverables and tasks. 7. Code the project following the 1.1, 1.1.1, 1.2 format. 8. Establish the project schedule by estimating time durations for all of your individual tasks. Enter the duration (in days) for each task. 9. Using a task’s Notes feature, justify the time estimates for at least 5 tasks. For example, you might make the following note: “This will take 3 days to allow the paint to dry before applying the trim.” 10. Enter at least 3 milestones for your project. Milestones typically use passive verbs (i.e. Phase 1 completed) and do not have any duration assigned to them (0 days). 11. Link all of your individual tasks and milestones. You can use the “link” button (appears as a chain link) after selecting the 2 tasks to be linked. Note that there are numerous ways to link tasks. Vary your linkages by including at least 2 relationships that are not Microsoft Project’s default (Finish-to-Start) relationships. 12. Not all tasks start immediately after a task ends (they “lag”) or wait until a task is completely finished before starting (they “lead”). Therefore, have at least 1 task include lead time or lag time. In the Notes section for this task, indicate why there would be a lead/lag for that particular task.
Answered 10 days AfterNov 21, 2022

Answer To: BUSI 681Proposed Project Model: Project File Assignment InstructionsOverviewPart 1 of your...

Dr Shweta answered on Dec 01 2022
42 Votes
SOLUTION.PDF

Answer To This Question Is Available To Download