BKAL1013 Business Accounting PART B: DIRECT MATERIALS AND DIRECT LABOR VARIANCES At the beginning of June, Faiz Mainan Sdn. Bhd. budgeted 5,000 toys action figures to be manufactured in June at...


BKAL1013 Business Accounting<br>PART B: DIRECT MATERIALS AND DIRECT LABOR VARIANCES<br>At the beginning of June, Faiz Mainan Sdn. Bhd. budgeted 5,000 toys action figures to be<br>manufactured in June at standard direct materials and direct labor costs as follows:<br>Direct materials<br>RM50,000<br>Direct labor<br>RM36.000<br>Total<br>RM86,000<br>The standard materials price is RM4.00 per pound. The standard direct labor rate is RM18.00<br>per hour. At the end of June, the actual direct materials and direct labor costs were as follows:<br>Actual direct materials<br>RM49,600<br>Actual direct labor<br>RM34,020<br>Total<br>RM83,620<br>There were no direct materials price or direct labor rate variance for June. In addition, assume<br>no charges in the direct materials inventory balances in June. Faiz Mainan Sdn. Bhd. actually<br>produced 4,850 units of toys action figures during June.<br>REQUIRED:<br>(a) Determine the direct materials quantity variance.<br>(b) Determine the direct labor time variance.<br>

Extracted text: BKAL1013 Business Accounting PART B: DIRECT MATERIALS AND DIRECT LABOR VARIANCES At the beginning of June, Faiz Mainan Sdn. Bhd. budgeted 5,000 toys action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials RM50,000 Direct labor RM36.000 Total RM86,000 The standard materials price is RM4.00 per pound. The standard direct labor rate is RM18.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials RM49,600 Actual direct labor RM34,020 Total RM83,620 There were no direct materials price or direct labor rate variance for June. In addition, assume no charges in the direct materials inventory balances in June. Faiz Mainan Sdn. Bhd. actually produced 4,850 units of toys action figures during June. REQUIRED: (a) Determine the direct materials quantity variance. (b) Determine the direct labor time variance.

Jun 11, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here