The steps will be to create a Testing Plan Make sure to create a Scope statement which will include: · Project Name · Project charter · Owner, sponsor, project manager, stakeholders · Problem...

1 answer below »
I need a price quote for the attached homework assignment.


The steps will be to create a Testing Plan Make sure to create a Scope statement which will include: · Project Name · Project charter · Owner, sponsor, project manager, stakeholders · Problem statement · Project Goals and Objectives · Project Requirements · Project Deliverables · Exclusions · Milestones · Cost estimates The steps will be to create a Testing Plan.  Prepare a proper APA paper which will need a title page; 12 pt. font; double-spaced, adding a role and responsibilities chart, and the following questions described and answered and a reference page. You have been asked to test and document enhancements to a web application that allows buyers to purchase custom-printed canvas shoes. The tasks and dependencies are as follows: · Create a testing plan (Research and Read about how to make a testing plan for software) Once the testing plan is ready, you you can: · Test the user interfaces · Test the database · Test the network · Write the documentation first draft We know this is simulated web application but make it as real as possible by being graphic. When the user interface tests are complete, you can: · Perform user testing—enlist some users to test the user interface. When the database and network testing are complete, you can: · Perform integration testing—network with the database When the user testing of the user interface and the database testing are complete, you can: · Perform integration testing—database, network, and user interface When all integration testing and user testing are complete, you can: · Perform system testing Then you can: · Review and revise documentation After all other tasks are complete, you can: · Obtain management approval Duration estimates for the tasks: (What would a manager approve?)   a.     3 days b.    10 days c.      6 days d.     7 days e.    20 days f.       5 days g.     3 days h.     2 days i.       8 days j.       4 days k.      5 days 1. Create a network diagram and a Gantt chart (research for a simple one and use Excel or a free template online) for the project. You are permitted to use software such as Microsoft Project to help you prepare your diagrams. 1. What is the planned duration for the testing project? 2. What is the critical path for the testing project? 3. For each task NOT on the critical path, calculate the amount of slack 4. If the user testing of the user interface takes 15 days, what will the impact be on the project duration? 2. Go online and find at least two sites with definitions of fast tracking and crashing a project schedule. 1. Prepare proper reference citations for the sites you located, using APA. 2. In your own words, write definitions for project fast tracking and project. 3. Consider the plan you prepared for the software system testing project in question 1 above. If you were informed by management that you must reduce the planned duration of the project by five days, describe how you, as a project manager, could crash or fast track this Be specific in identifying exactly what could be changed in the project plan for each option. 4. (continuation of question 3) If the request to speed up the project occurs after day 25 of the original schedule, what is the only option available?                                       3. Go online and research the difference between total slack and free.
Answered Same DaySep 05, 2021

Answer To: The steps will be to create a Testing Plan Make sure to create a Scope statement which will include:...

Tanmoy answered on Sep 06 2021
136 Votes
The steps will be to create a Testing Plan
Make sure to create a Scope statement which will include:
· Project Name
· Project charter
· Owner, sponsor, project manager, stakeholders
· Problem statement
· Project Goals and Objectives
· Project Requirements
· Project Deliverables
· Exclusions
· Mile
stones
· Cost estimates
The steps will be to create a Testing Plan. 
Prepare a proper APA paper which will need a title page; 12 pt. font; double-spaced, adding a role and responsibilities chart, and the following questions described and answered and a reference page.
You have been asked to test and document enhancements to a web application that allows buyers to purchase custom-printed canvas shoes. The tasks and dependencies are as follows:
· Create a testing plan (Research and Read about how to make a testing plan for software)
Once the testing plan is ready, you you can:
· Test the user interfaces
· Test the database
· Test the network
· Write the documentation first draft
We know this is simulated web application but make it as real as possible by being graphic.
When the user interface tests are complete, you can:
· Perform user testing—enlist some users to test the user interface.
When the database and network testing are complete, you can:
· Perform integration testing—network with the database
When the user testing of the user interface and the database testing are complete, you can:
· Perform integration testing—database, network, and user interface When all integration testing and user testing are complete, you can:
· Perform system testing Then you can:
· Review and revise documentation
After all other tasks are complete, you can:
· Obtain management approval Duration estimates for the tasks: (What would a manager approve?)
 
    a.     3
    days
    b.    10
    days
    c.      6
    days
    d.     7
    days
    e.    20
    days
    f.       5
    days
    g.     3
    days
    h.     2
    days
    i.       8
    days
    j.       4
    days
    k.      5
    days
1. Create a network diagram and a Gantt chart (research for a simple one and use Excel or a free template online) for the project. You are permitted to use software such as Microsoft Project to help you prepare your diagrams.
1. What is the planned duration for the testing project?
The testing project will initiate from start date to end date and it is the planned duration of the project. The project will begin from 4th November, 2021 and will be completed by 24th December, 2021. The duration of the project is measured using the business working hours which is Monday to Friday in this case. The duration of the project does not include the end date for the purpose of calculation. Also, the holidays were not considered at the time of calculating the duration of the project. The planned duration of this project is considered to be 37 days.
2. What is the critical path for the testing project?
The critical path of the project is the flowchart which is there within the network of various activities. This allows the project to be completed within the shortest...