I need this entire assignment completed correctly.


3/20/2021 Question 1 - Wk 2 - Practice: Planning for Capital Investments [due Sat] - Connect https://ezto.mheducation.com/ext/map/index.html?_con=con&external_browser=0&launchUrl=https%253A%252F%252Flms.mheducation.com%252F… 1/1 eBook Print References 1 20 points Wk 2 - Practice: Planning for C…  Help Save & Exit SubmitSaved Check my work Dwight Donovan, the president of Baird Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of five years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $105,000 and for Project B are $32,000. The annual expected cash inflows are $26,995 for Project A and $8,877 for Project B. Both investments are expected to provide cash flow benefits for the next five years. Baird Enterprises’ desired rate of return is 6 percent. (PV of $1 and PVA of $1) (Use appropriate factor(s) from the tables provided.) Required a. Compute the net present value of each project. Which project should be adopted based on the net present value approach? b. Compute the approximate internal rate of return of each project. Which one should be adopted based on the internal rate of return approach?  Required A Required B  Complete this question by entering your answers in the tabs below. Compute the net present value of each project. Which project should be adopted based o (Round your final answers to 2 decimal places.) Required A Required B Net Present Value Project A Project B Which project should be adopted? Prev of 1 Next ← 1 ▦ → https://ezto.mheducation.com/hm.tpx?todo=c15SinglePrintView&singleQuestionNo=1.&postSubmissionView=13252712542820991&wid=13252712699005339&role=student&pid=24954172_3768439261_1_128910371 https://createwp.customer.mheducation.com/wordpress-mu/success-academy-student/help-getting-to-know-connect/#.VYw1OU9VhBd https://ezto.mheducation.com/extMedia/bne/accounting/edmonds_fmac_9e/pv_of_$1.jpg https://ezto.mheducation.com/extMedia/bne/accounting/edmonds_fmac_9e/pva_of_$1.jpg
Answered Same DayMar 20, 2021

Answer To: 3/20/2021 Question 1 - Wk 2 - Practice: Planning for Capital Investments [due Sat] - Connect...

Chirag answered on Mar 21 2021
143 Votes
Sheet1
    Net Present Value        $
    Project A    =    8714
    Project B    =    5393
    Which Project Should be Accept
ed        Project A
    Internal Rate of Return        $
    Project A    =    9%
    Project B    =    12%
    Which Project Should be Accepted        Project B
    Net Present Value    
    Project A    Year    Value    PF @ 6%    PV
    Initial Cost    0    $...