II Develop a​lot-for-lot solution and calculate total relevant costs for the gross requirements in the following​table*. Period 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 30 30 60 20 20 80 50...

1 answer below »
II








Develop a​lot-for-lot solution and calculate total relevant costs for the gross requirements in the following​table*.
































Period123456789101112
Gross requirements2030306020208050
​*Holding cost=​$2.50​/unit/week; setup cost=​$150​; lead time=1 ​week; beginning inventory=40.Develop a​lot-for-lot solution ​(enter your responses as whole numbers​).


































































































Period123456789101112
Gross requirements2030306020208050
​On-hand at beginning of period40404020202020000000000000000000
​On-hand at end of periodnothingnothingnothingnothingnothingnothingnothingnothingnothingnothingnothingnothing
Order receiptnothingnothingnothingnothingnothingnothingnothingnothingnothingnothingnothing
Order releasenothingnothingnothingnothingnothingnothingnothingnothingnothingnothingnothing










Develop a​lot-for-lot solution and calculate total relevant costs for the gross requirements in the following​table*.



HW12(ch.14)-Rojin Sabahi Chamachaee 5/10/2021 HW12(ch.14)-Rojin Sabahi Chamachaee https://xlitemprod.pearsoncmg.com/api/v1/print/en-us/om 1/5 1. Student: Rojin Sabahi Chamachaee Date: 5/10/21 Instructor: Ahmad Vessal Course: SOM 306 OPERATIONS MGMT - (14022-SP2021) Assignment: HW12(ch.14) The demand for subassembly S is 100 units in week 7. Each unit of S requires unit of T and unit of U. Each unit of T requires unit of V, unit of W, and unit of X. Finally, each unit of U requires unit of Y and units of Z. One firm manufactures all items. It takes 2 weeks to make S, week to make T, 2 weeks to make U, week to make V, weeks to make W, week to make X, 2 weeks to make Y, and week to make Z. 1 1 2 s 2 s 1 2 s 2 2 s 2 s 2 2 s 1 a) Choose the correct product structure. A. B. C. D. b) Choose the correct time-phased product structure. A. 7654321 Time in weeks B. 1 2 3 4 5 6 7 Time in weeks C. 1 2 3 4 5 6 7 Time in weeks D. 1 2 3 4 5 6 7 Time in weeks 2 1 0 S T(1) V(2) U(1) Z(2)Y(2) W(2) X(1) Level 2 1 0 S V(2) U(1) Y(2) Z(2)T(1) W(2) X(1) Level 2 1 0 S T(1) U(1) Y(2) Z(2)V(2) W(2) X(1) Level 2 1 0 S U(1) T(1) W(2) X(1)V(2) Y(2) Z(2) Level S T U Y Z V W X S T U Y Z V W X S T U Y Z V W X S T U Y Z V W X 5/10/2021 HW12(ch.14)-Rojin Sabahi Chamachaee https://xlitemprod.pearsoncmg.com/api/v1/print/en-us/om 2/5 2. 1: More Info The demand for subassembly S is units in week 7. Each unit of S requires unit of T and unit of U. Each unit of T requires unit of V, unit of W, and unit of X. Finally, each unit of U requires unit of Y and units of Z. One firm manufactures all items. It takes 2 weeks to make S, week to make T, 2 weeks to make U, week to make V, weeks to make W, week to make X, 2 weeks to make Y, and week to make Z. 140 1 1 2 s 2 s 1 1 3 2 s 2 s 2 1 2 s Click the icon to view the product structure and the time-phased product structure.1 Construct a gross material requirements plan (type 0 if the input box is not used). Week Item 1 2 3 4 5 6 7 S Gross req 0 0 0 0 0 0 140 Order release 0 0 0 0 140 0 0 TGross req 0 0 0 0 140 0 0 Order release 0 0 140 0 0 0 0 2 UGross req 0 0 0 0 140 0 0 Order release 0 0 140 0 0 0 0 VGross req 0 0 280 0 0 0 0 Order release 280 0 0 0 0 0 0 WGross req 0 0 280 0 0 0 0 Order release 280 0 0 0 0 0 0 XGross req 0 0 140 0 0 0 0 Order release 0 140 0 0 0 0 0 YGross req 0 0 140 0 0 0 0 Order release 140 0 0 0 0 0 0 ZGross req 0 0 420 0 0 0 0 Order release 420 0 0 0 0 0 0 2 The product structure. The time-phased product structure. 1 2 3 4 5 6 7 Time in weeks YOU ANSWERED: 0 0 2 1 0 S T(1) U(1) Y(1) Z(3)V(2) W(2) X(1) Level S T U Y Z V W X 5/10/2021 HW12(ch.14)-Rojin Sabahi Chamachaee https://xlitemprod.pearsoncmg.com/api/v1/print/en-us/om 3/5 3. 2: More Info The demand for subassembly S is units in week 7. Each unit of S requires unit of T and unit of U. Each unit of T requires unit of V, unit of W, and unit of X. Finally, each unit of U requires unit of Y and units of Z. One firm manufactures all items. It takes 2 weeks to make S, week to make T, 2 weeks to make U, week to make V, weeks to make W, week to make X, 2 weeks to make Y, and week to make Z. 80 2 s 1 2 s 1 1 1 2 1 2 s 3 1 2 s Click the icon to view the product structure and the time-phased product structure.2 In addition to units of S, there is also a demand for units of U, which is a component of S. The units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). 80 20 20 Week Item 1 2 3 4 5 6 7 S Gross req 0 0 0 0 0 0 80 Order release 0 0 0 0 80 0 0 TGross req 0 0 0 0 160 0 0 Order release 0 0 0 160 0 0 0 UGross req 0 0 0 0 80 20 0 Order release 0 0 80 20 0 0 0 VGross req 0 0 0 320 0 0 0 Order release 0 320 0 0 0 0 0 WGross req 0 0 0 80 0 0 0 Order release 80 0 0 0 0 0 0 XGross req Order release YGross req Order release ZGross req Order release 2 The product structure. The time-phased product structure. 1 2 3 4 5 6 7 Time in weeks 2 1 0 S T(2) U(1) Y(1) Z(2)V(2) W(1) X(1) Level S T U Y Z V W X 5/10/2021 HW12(ch.14)-Rojin Sabahi Chamachaee https://xlitemprod.pearsoncmg.com/api/v1/print/en-us/om 4/5 4. 5. YOU ANSWERED: 0 0 160 140 20 Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*.                                                                                     Period 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 30 30 60 20 20 80 50 *Holding cost $ /unit/week; setup cost $ ; lead time 1 week; beginning inventory 40.= 2.50 = 150 = = Develop a lot-for-lot solution (enter your responses as whole numbers ). Period 1 2 3 4 5 6 7 Gross requirements 20 30 30 60 20 On-hand at beginning of period 40 On-hand at end of period Order receipt Order release The total cost is $ (enter your response as a whole number ). Consider the following product structure. If the demand for product A is 40 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed? A. 70 B. 3 C. 100 D. 90 E. 40 5/10/2021 HW12(ch.14)-Rojin Sabahi Chamachaee https://xlitemprod.pearsoncmg.com/api/v1/print/en-us/om 5/5 6. 7. Consider the following requirements for an office chair product. Week 1 2 3 4 5 6 Gross requirements 100 100 400 500 0 400 The company has a setup cost of $100, a holding cost per week of $5, beginning inventory of 100, and lead time of 1 week. If a lot-for-lot policy is used, what will be the total setup cost for this six-week inventory period? $100 $200 $400 $300 $500 An order for 100 units of Product A has been placed. There are currently 60 units of Product A on hand. Each A requires 4 units of Part B. There are 20 units of B available. What are the net requirements for B? A. 140 B. 380 C. 180 D. 160 E. 20
Answered Same DayMay 11, 2021

Answer To: II Develop a​lot-for-lot solution and calculate total relevant costs for the gross requirements in...

Sultana answered on May 11 2021
136 Votes
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here