Project Risks, Risk Register, and Risk Analysis Halifax City has been approved to host the Olympic Games. Now the work begins. A project team has been identified to lead the project, and planning has...

1 answer below »

Project Risks, Risk Register, and Risk Analysis


Halifax City has been approved to host the Olympic Games. Now the work begins. A project team has been identified to lead the project, and planning has begun. A number of things have to happen on time and virtually simultaneously in order to ensure a successful hosting of the games.


Here are the three things I'd like you to do:



  1. Identify possible risks to the project. A risk is a specific event or condition that has an impact on at least one project objective. See PMBOK ® Guide Chapter 11, pages 409-417 and the lecture video for further reference.

  2. Develop a probability and impact matrix to establish an initial priority of risks. See PMBOK ® Guide Chapter 11, pages 419-427 for further reference.

  3. Develop risk responses to identified risks. The responses should be specific actions taken to effectively address the risk (Avoid, transfer, mitigate or accept alone is insufficient). See PMBOK ® Guide Chapter 11, pages 437-441 for further reference.

Answered Same DayNov 11, 2021

Answer To: Project Risks, Risk Register, and Risk Analysis Halifax City has been approved to host the Olympic...

Sudipta answered on Nov 13 2021
137 Votes
1. Identify possible risks to the project
To complete the project for hosting Olympic Games in Halifax Cit
y several risks can takes place. Some possible risk that could take place in this project is identified in the following section.
· Project delay risk: Several protests from local business owners could take place during the construction process of the project. if such issue takes place then project manager won’t be able to deliver the project within given deadline. As a result, project delay will take place and it will hamper successful completion of the host.
· Financial risk: Financial risk and project delay risk is completely associated with each other. If protest from local business take place then workflow in the project will get halted however, project manager won’t stop the payment of the project staffs. As a result, expenses will get increase one side and work won’t be done at the other side. This will be an expensive process and financial risk will take place.
· Legal risk: A number of legal approvals should be taken into account before...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here