check the file
Project Work Breakdown Structure (Team project) Project WBS Fall 2021 Page 1 of 6 Overview The purpose of this Team assignment is to: • Determine the work required to build Mamma Mia's IT system. • List all deliverable end items in the form of Summary Tasks. • Define and list sub-tasks under each Summary Task. • Produce a final WBS. There are three parts to this assignment. Part 1 - Team-reviewed Project Charter in Microsoft Word In Week 2, each of your team members created a Project Charter. Your team needs only one Project Charter. As a team, select one Charter to use for this assignment. Be sure to update it using the assignment feedback from Week 2, the Case Study, and deliverable and task elements specified in Part 2 of this assignment. The Charter and the project WBS must align with each other. IMPORTANT: The submission file should be named as "Group" "Team Name" "Deliverable for" "Assignment Name", such as - Group A Projecteers Charter for Project WBS.docx Part 2 - Work Breakdown Structure in Microsoft Project Re-read the following: • "How to Build Work Breakdown Structures" (Week 1 → Reading), paying close attention to o WBS Creation process o Definitions o Convention for WBS structure o Considerations for building the WBS o Schedule development process o Naming Terminology • "What NOT to do in a WBS" (Week 1 → Reading) Before creating the WBS, open a blank project in Microsoft Project. Apply the settings from the Project Configuration Settings section in "Project Tutorials" (Course Resources). As a team, develop and submit a project work breakdown structure (WBS) in Microsoft Project's .mpp format. Your WBS should include all work necessary to complete the scope of the project, specifically including the technical IT work of the project. The WBS should include the project management effort as well. This is the work the Project Manager (and team) must do to keep the project moving in the right direction. It would include such things as team and customer meetings, briefs to the sponsor, status reports, and so on. At this stage, the Project WBS should not include: • Duration estimates (just leave it at the "1d" default value) • Predecessor-successor links (aka dependencies) • Resource data (cost, names, etc.). Project Work Breakdown Structure (Team project) Project WBS Fall 2021 Page 2 of 6 Here are some Level 2 WBS elements you should include (among others), not necessarily in the order shown: • IT System Design • System Hardware • System Software • System Networking • System Test • Project Management • System Transition With respect to hardware, software, and networking - lower level WBS elements will deal with Orders, Delivery, Receiving, Installation, etc. Make sure that your WBS (and .mpp file) include the following tasks as part of your WBS. These are necessary but more tasks may well be needed. This also does not mean that a single task will necessarily suffice for each of these. Rather, include as many tasks as it takes to do the job, but please include at least the following kinds of tasks in addition to whatever else you were planning for your WBS: • Ordering, and receiving hardware • Ordering, and receiving software • Ordering, and receiving networking • Installing hardware • Installing software • Installing networking • Managing, controlling, and monitoring the project and the team • Project status reports There is a lot more to the WBS than this. Do not spend too much time getting "down into the weeds". A good size for this class would be no more than 10 Level 2 elements. Decompose these to Level 3 elements (or Level 4 if absolutely necessary). Remember, the lowest level elements (those with indented sub-tasks, not indented summary tasks) will be your work packages. Finally, define and list sub-tasks within each work package. Project Work Breakdown Structure (Team project) Project WBS Fall 2021 Page 3 of 6 Formatting Your Project WBS Use the Insert Column function (read about this in "Project Tutorials" → Show the Project WBS Numbers) so the Project WBS shows the following columns (in this order): • Indicators (column shows ) • Task Mode • Constraint Type • Constraint Date • Outline Level • WBS • Task Name • Duration • Start • Finish • Predecessors • Successors • Type IMPORTANT: The submission file should be named as "Group" "Team Name" "Deliverable for" "Assignment Name", such as - Group A Projecteers Project File for Project WBS.mpp Project Work Breakdown Structure (Team project) Project WBS Fall 2021 Page 4 of 6 Part 3. Answers to Questions in Microsoft Word Read and think through the options and alternatives suggested by these questions before you build your Project WBS. When your Project WBS is completed, answer the following questions, and submit them as a Microsoft Word document. "Yes" or "No" answers with no explanations or discussions are not appropriate answers. 1. Does the Project Schedule include everything in your team's charter and all deliverables? If the WBS includes tasks that were not part of the Project Charter, explain how the team determined the additional tasks were necessary. 2. Does the WBS include project management tasks necessary to manage the project? 3. Explain the top-down and bottom-up approaches to building a WBS. Which approach did the team decide to use and why did they make that decision? 4. Building the WBS as an outline in Word or Excel instead of Project can help team members visualize the order of the tasks and how the tasks might decompose into lower levels. Did the team build an outline outside of Project? If you only used Project, did the team need to rearrange tasks while building the WBS? 5. Did the team approach the WBS graphically (like an organization chart) or tabularly (like a list or table), or something else? Why? 6. Did the team work together to determine the major tasks or was only one team member responsible for that? How well did it work? Project Work Breakdown Structure (Team project) Project WBS Fall 2021 Page 5 of 6 Formatting Your Questions Document • Create an APA format title page that includes: The title of report (Questions for Project WBS), your name, Course and Section number and date (use assignment due date); do not include graphics or themes. • No running header required for this document. • The body of the paper should be double (or 1.5") spaced, and no longer than 5 pages. • Answers should be formatted as normal sentences (no numbering, not a run-on sentence as part of the question, no indenting). • Use 1" margins on all sides. • Font should be 11-point Calibri, 11-point Arial, 10-point Lucida Sans Unicode, 12-point Times New Roman, 11-point Georgia, or 10-point Computer Modern. • Font should remain consistent throughout the paper, i.e., not changing from one font to another. • Use at least one external reference and one from the course content (from the class reading content, not the assignment instructions or case study itself) with APA formatted citation and reference. For information on general APA format and specifics related to citing from the class content, refer to Content → Course Resources → Writing Resources. Resources must not use Wikipedia, general information sites, blogs, or discussion groups. • The list of References must be its own page at the end of the document and it must be in APA format, i.e., double spaced, .5" hanging indent. No more than 10% of the paper may be in the form of a direct citation from an external source. All in-text citations must appear in the References list and all entries in the References list must be used as in-text citations. • Run Microsoft Word's grammar/spell checker; there should be no errors in grammar, verb tenses, pronouns, spelling, punctuation, first person usage, or contractions. • Submit your paper as a Word document, or a document that can be read in Word. IMPORTANT: The submission file should be named as "Group" "Team Name" "Deliverable for" "Assignment Name", such as - Group A Projecteers Questions for Project WBS.docx Project Work Breakdown Structure (Team project) Project WBS Fall 2021 Page 6 of 6 Grading Rubric Criteria 90-100% Far Above Standards 80-89% Above Standards 70-79% Meets Standards 60-69% Below Standards< 60% well below standards possible points team-reviewed project charter updated charter revised to match scope and wbs. 5 points scope and deliverables fully updated and aligned with wbs. 4 points scope and deliverables mostly updated and aligned with wbs. 3 points scope and deliverables moderately updated and aligned with wbs. 2 points scope and deliverables somewhat updated and aligned with wbs. 0-1 points scope and deliverables not updated or aligned with wbs. 5 configuration settings needed for producing consistent results in the project wbs. 5 points all configuration settings correct. 4 points missed 1-2 configuration settings. 3 points missed 3-4 configuration settings. 2 points missed 4-5 configuration settings. 0-1 points missed 5 or more configuration settings. 5 work breakdown structure wbs is decomposed to level 4, uses project's wbs numbering, rows are continuous, includes specified wbs elements, satisfies scope of the project charter. 9-10 points correctly decomposed the schedule, no blank rows, included all specified wbs elements, all deliverables align to the project charter. 8 points decomposed too little (level 3), or too much (level 5); included a few more (or less) than 10 level 2 elements; most of the specified lower level elements, project management elements, and/or deliverables aligned to the project charter. 7 points under-decomposition (level 2), or over-decomposition (level 6); missing several of the specified lower level elements, project management elements, and/or deliverables aligned to the project charter. 6 points too much decomposition (beyond level 6); only includes some of the specified lower level elements, project management elements, and/or deliverables aligned to the project charter. 0-5 points no decomposition at all (stopped at level 1); left blank rows in the schedule, includes few of the specified lower level elements, project management elements, and/or deliverables aligned to the project charter. 10 schedule structure no durations, resources, dependencies, or costs specified. includes project start and project complete. 18-20 points no durations, resources, dependencies, or costs; first task is project start milestone, last task is project complete milestone. 16-17 points applied some durations, resources, dependencies, or costs; loaded most sub-task durations and some start/finish dates. 14-15 points applied several durations, resources, dependencies, or costs; loaded several sub- task durations but also several start/finish dates. 12-13 points applied many durations, resources, dependencies, or costs; loaded some sub- task durations and ms- project calculates some start/finish dates. 0-11 points applied durations, resources, dependencies, and costs; loaded all sub-task durations so ms-project cannot calculate start/finish dates; first task is not project start milestone, and last task is not project complete milestone. 20 schedule details tasks describe work/deliverables (not a checklist) using provided naming conventions. 125 rows or less, columns reveal specified fields. no color-coding, special characters, or task names with full sentences. 18-20 points row count is 125. all tasks follow correct naming convention, do not encompass multiple deliverables/actions, or use full sentences. color-coding and special characters are not used. columns reveal all specified fields. 16-17 points row count is a little over 125. 1-2 tasks use incorrect naming convention, use full sentences 60%="" well="" below="" standards="" possible="" points="" team-reviewed="" project="" charter="" updated="" charter="" revised="" to="" match="" scope="" and="" wbs.="" 5="" points="" scope="" and="" deliverables="" fully="" updated="" and="" aligned="" with="" wbs.="" 4="" points="" scope="" and="" deliverables="" mostly="" updated="" and="" aligned="" with="" wbs.="" 3="" points="" scope="" and="" deliverables="" moderately="" updated="" and="" aligned="" with="" wbs.="" 2="" points="" scope="" and="" deliverables="" somewhat="" updated="" and="" aligned="" with="" wbs.="" 0-1="" points="" scope="" and="" deliverables="" not="" updated="" or="" aligned="" with="" wbs.="" 5="" configuration="" settings="" needed="" for="" producing="" consistent="" results="" in="" the="" project="" wbs.="" 5="" points="" all="" configuration="" settings="" correct.="" 4="" points="" missed="" 1-2="" configuration="" settings.="" 3="" points="" missed="" 3-4="" configuration="" settings.="" 2="" points="" missed="" 4-5="" configuration="" settings.="" 0-1="" points="" missed="" 5="" or="" more="" configuration="" settings.="" 5="" work="" breakdown="" structure="" wbs="" is="" decomposed="" to="" level="" 4,="" uses="" project's="" wbs="" numbering,="" rows="" are="" continuous,="" includes="" specified="" wbs="" elements,="" satisfies="" scope="" of="" the="" project="" charter.="" 9-10="" points="" correctly="" decomposed="" the="" schedule,="" no="" blank="" rows,="" included="" all="" specified="" wbs="" elements,="" all="" deliverables="" align="" to="" the="" project="" charter.="" 8="" points="" decomposed="" too="" little="" (level="" 3),="" or="" too="" much="" (level="" 5);="" included="" a="" few="" more="" (or="" less)="" than="" 10="" level="" 2="" elements;="" most="" of="" the="" specified="" lower="" level="" elements,="" project="" management="" elements,="" and/or="" deliverables="" aligned="" to="" the="" project="" charter.="" 7="" points="" under-decomposition="" (level="" 2),="" or="" over-decomposition="" (level="" 6);="" missing="" several="" of="" the="" specified="" lower="" level="" elements,="" project="" management="" elements,="" and/or="" deliverables="" aligned="" to="" the="" project="" charter.="" 6="" points="" too="" much="" decomposition="" (beyond="" level="" 6);="" only="" includes="" some="" of="" the="" specified="" lower="" level="" elements,="" project="" management="" elements,="" and/or="" deliverables="" aligned="" to="" the="" project="" charter.="" 0-5="" points="" no="" decomposition="" at="" all="" (stopped="" at="" level="" 1);="" left="" blank="" rows="" in="" the="" schedule,="" includes="" few="" of="" the="" specified="" lower="" level="" elements,="" project="" management="" elements,="" and/or="" deliverables="" aligned="" to="" the="" project="" charter.="" 10="" schedule="" structure="" no="" durations,="" resources,="" dependencies,="" or="" costs="" specified.="" includes="" project="" start="" and="" project="" complete.="" 18-20="" points="" no="" durations,="" resources,="" dependencies,="" or="" costs;="" first="" task="" is="" project="" start="" milestone,="" last="" task="" is="" project="" complete="" milestone.="" 16-17="" points="" applied="" some="" durations,="" resources,="" dependencies,="" or="" costs;="" loaded="" most="" sub-task="" durations="" and="" some="" start/finish="" dates.="" 14-15="" points="" applied="" several="" durations,="" resources,="" dependencies,="" or="" costs;="" loaded="" several="" sub-="" task="" durations="" but="" also="" several="" start/finish="" dates.="" 12-13="" points="" applied="" many="" durations,="" resources,="" dependencies,="" or="" costs;="" loaded="" some="" sub-="" task="" durations="" and="" ms-="" project="" calculates="" some="" start/finish="" dates.="" 0-11="" points="" applied="" durations,="" resources,="" dependencies,="" and="" costs;="" loaded="" all="" sub-task="" durations="" so="" ms-project="" cannot="" calculate="" start/finish="" dates;="" first="" task="" is="" not="" project="" start="" milestone,="" and="" last="" task="" is="" not="" project="" complete="" milestone.="" 20="" schedule="" details="" tasks="" describe="" work/deliverables="" (not="" a="" checklist)="" using="" provided="" naming="" conventions.="" 125="" rows="" or="" less,="" columns="" reveal="" specified="" fields.="" no="" color-coding,="" special="" characters,="" or="" task="" names="" with="" full="" sentences.="" 18-20="" points="" row="" count="" is="" 125.="" all="" tasks="" follow="" correct="" naming="" convention,="" do="" not="" encompass="" multiple="" deliverables/actions,="" or="" use="" full="" sentences.="" color-coding="" and="" special="" characters="" are="" not="" used.="" columns="" reveal="" all="" specified="" fields.="" 16-17="" points="" row="" count="" is="" a="" little="" over="" 125.="" 1-2="" tasks="" use="" incorrect="" naming="" convention,="" use="" full=""> 60% well below standards possible points team-reviewed project charter updated charter revised to match scope and wbs. 5 points scope and deliverables fully updated and aligned with wbs. 4 points scope and deliverables mostly updated and aligned with wbs. 3 points scope and deliverables moderately updated and aligned with wbs. 2 points scope and deliverables somewhat updated and aligned with wbs. 0-1 points scope and deliverables not updated or aligned with wbs. 5 configuration settings needed for producing consistent results in the project wbs. 5 points all configuration settings correct. 4 points missed 1-2 configuration settings. 3 points missed 3-4 configuration settings. 2 points missed 4-5 configuration settings. 0-1 points missed 5 or more configuration settings. 5 work breakdown structure wbs is decomposed to level 4, uses project's wbs numbering, rows are continuous, includes specified wbs elements, satisfies scope of the project charter. 9-10 points correctly decomposed the schedule, no blank rows, included all specified wbs elements, all deliverables align to the project charter. 8 points decomposed too little (level 3), or too much (level 5); included a few more (or less) than 10 level 2 elements; most of the specified lower level elements, project management elements, and/or deliverables aligned to the project charter. 7 points under-decomposition (level 2), or over-decomposition (level 6); missing several of the specified lower level elements, project management elements, and/or deliverables aligned to the project charter. 6 points too much decomposition (beyond level 6); only includes some of the specified lower level elements, project management elements, and/or deliverables aligned to the project charter. 0-5 points no decomposition at all (stopped at level 1); left blank rows in the schedule, includes few of the specified lower level elements, project management elements, and/or deliverables aligned to the project charter. 10 schedule structure no durations, resources, dependencies, or costs specified. includes project start and project complete. 18-20 points no durations, resources, dependencies, or costs; first task is project start milestone, last task is project complete milestone. 16-17 points applied some durations, resources, dependencies, or costs; loaded most sub-task durations and some start/finish dates. 14-15 points applied several durations, resources, dependencies, or costs; loaded several sub- task durations but also several start/finish dates. 12-13 points applied many durations, resources, dependencies, or costs; loaded some sub- task durations and ms- project calculates some start/finish dates. 0-11 points applied durations, resources, dependencies, and costs; loaded all sub-task durations so ms-project cannot calculate start/finish dates; first task is not project start milestone, and last task is not project complete milestone. 20 schedule details tasks describe work/deliverables (not a checklist) using provided naming conventions. 125 rows or less, columns reveal specified fields. no color-coding, special characters, or task names with full sentences. 18-20 points row count is 125. all tasks follow correct naming convention, do not encompass multiple deliverables/actions, or use full sentences. color-coding and special characters are not used. columns reveal all specified fields. 16-17 points row count is a little over 125. 1-2 tasks use incorrect naming convention, use full sentences>