Based on the table shown below identify the Critical Path (draw the network diagram considering day 1 as the first day of the project. Answers to questions are based on the diagram considering day 1 as the first day of the project).
(a) Path HIJ
(b) Path ABFG
(c) Path EFG
(d) Path ABCD
What is the duration of path ABFG?
(a) 30 days
(b) 25 days
(c) 17 days
(d) 35 days