Question: 155 Based on the table shown below identify the Critical Path (draw the network diagram considering day 1 as the first day of the project. Answers to questions are based on the diagram...


Question: 155

Based on the table shown below identify the Critical Path (draw the network diagram considering day 1 as the first day of the project. Answers to questions are based on the diagram considering day 1 as the first day of the project).






(a) Path HIJ


(b) Path ABFG


(c) Path EFG


(d) Path ABCD


Question: 156

What is the duration of path ABFG?




(a) 30 days


(b) 25 days


(c) 17 days


(d) 35 days







May 07, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here