GSGM7344 Project Management Assignment 2 – Crashing Assignment Name: Matric number: You are given the following network diagram. 1. Perform the activities crashing until it can no longer be crashed....

1 answer below »
This subject is related to project management, please assign a good expert to answer the question. I don't question to ask when i receive the answer like previous assignment.


GSGM7344 Project Management Assignment 2 – Crashing Assignment Name: Matric number: You are given the following network diagram. 1. Perform the activities crashing until it can no longer be crashed. What is the total cost? 2. If there is a bonus of $125 per day for finishing early, what activities would be crashed, and how fast would the project be completed? **End of Assignment 2 Questions** CRASHING ASSIGNMENT Activity Normal Time Normal Cost Crash Time Crash Cost A 5 $300 5 $300 B 8 250 5 400 C 2 100 2 100 D 6 300 3 600 E 3 150 2 300 F 4 275 3 300 G 9 700 8 900 Given the above network diagram: 1) perform the activities crashing until it can no longer be crashed. What is the total cost? 2) If there is a bonus of $125 per day for finishing early, what activit ies would be crashed, and how fast would the project be completed?
Answered 1 days AfterFeb 02, 2021

Answer To: GSGM7344 Project Management Assignment 2 – Crashing Assignment Name: Matric number: You are given...

Tanmoy answered on Feb 04 2021
135 Votes
Assignment 2 – Crashing Assignment
1. Perform the activities crashing until it can no longer be crashed. What is the total cost?
    Activity
    Normal Time

    Normal Cost
    Crash Time
    Crash Cost
    Expedite Cost Slope
    A
    5
    300
    5
    300
    0
    B
    8
    250
    5
    400
    50
    C
    2
    100
    2
    100
    0
    D
    6
    300
    3
    600
    100
    E
    3
    150
    2
    300
    150
    F
    4
    275
    3
    300
    25
    G
    9
    700
    8
    900
    200
     
     
    2075
     
     
    525
As per the details provided in the network diagram and the matrix, the Normal Cost is $2075 for activity A to G. To calculate the expedite cost slope for activities A to G we have used the formula of (Normal Cost – Crash Cost) ÷ (Normal Time – Crash Time). Expedite cost slope is extremely important as it is used to calculate the minimum cost that is used to evaluate the critical paths. The below are the critical paths as per the above network diagram that can be derived.
    Critical Paths
    Length of the Critical Paths
    A-B-E-G
    25
    A-C-E-G
    19
    A-C-F-G
    20
    A-D-F-G
    24
As per the four critical paths we have added the normal time for each of the activity of the critical paths in order to find the length of the critical path. For example: The length of critical path of A-B-E-G was derived by adding 5+8+3+8 = 25 and similarly for the other three critical paths. We can observe that the length of the critical path A-B-E-G was the highest with 25 while the length of critical path A-C-E-G was the lowest with 19. Our aim is to reduce the critical path with highest duration of 25 by...