https://account.cengage.com/login Username is: XXXXXXXXXX Password is: T@cos2021 Once on the Cengage portal click on course MS3053 Management Science and Operations Technology. Next click on chapter 4...

1 answer below »
Will require help with 5 questions within my Cengage homework portal.https://account.cengage.com/login


https://account.cengage.com/login Username is: [email protected] Password is: T@cos2021 Once on the Cengage portal click on course MS3053 Management Science and Operations Technology. Next click on chapter 4 Homework II.
Answered 12 days AfterSep 11, 2021

Answer To: https://account.cengage.com/login Username is: XXXXXXXXXX Password is: T@cos2021 Once on the Cengage...

Abhishek answered on Sep 17 2021
134 Votes
Component
    Manufacture
    Purchase
    Frame
    113
    4887
    Support
    0
    10000
    Strap
    0
    5000
1.
a.
b. Total cost- 415913
    Cutting
    340
    Milling
    227
    Shaping
    295
c.
d. Shaping department has excess hours(slack)
Slack = 650-295 = 355 hours
Therefore , there is no need to by hours for shaping
$0  because there is slack  of 355 hours
e. Reduced cost is 0, if more frames are available it would not negatively affect the optimal solution.
Therefore, the frame price can be less than $47.Yes . Because the current purchase price is $47. The reduced cost is $0 which means that the solution may be improved if the...