Central Queensland University XXXXXXXXXXPPMP20011: Contract & Procurement XXXXXXXXXXmanagement XXXXXXXXXXIndividual Practical Assessment: (40% XXXXXXXXXX % Report+ 10% Peer Assessment)...

1 answer below »
word count as per the question


Central Queensland University PPMP20011: Contract & Procurement management Individual Practical Assessment: (40%) (30 % Report+ 10% Peer Assessment) Assessment Due date: Week 8; Sep. 7.2020 Central Queensland University PPMP20011: Contract & Procurement management Individual Practical Assessment: (40%) (30 % Report+ 10% Peer Assessment) Assessment Due date: Week 8; Sep. 7.2020 2020 UNIT COORDINATOR: DR ZIYAD ABUNADA | PPMP20011 Assessment 1 (30%+10%) Aug- Sep. 2020 Introduction: Due to the unprecedented conditions resulted from Covid 19, and the impact on the international students joining Central Queensland University (CQU), CQU is aiming to increase the numbers of the domestic students and therefore CQU aims to open new facilities and new campus at regional areas. For this purpose, CQuniversity is proposing a project detailed below to meet the increasing student’s numbers as well as to provide a proper university life. It has purchased a new land of 40 Acers to construct its new project with the below elements: Project Elements: CQU is looking forward to including the following elements in the new project: 1. Main lecture building (can accommodate 500 Students) 2. Computer and engineering Laboratories 3. Conference hall with up to date facilities and infrastructure (250 people) Important notes: • This should create positive image within the local community. The new campus should be prestigious one finished to high quality standards. This needs to be balanced with the project cost being kept within budget and completed as soon as possible., with all parts of the development completed t the same time • CQU directors have indicated they have extensive knowledge in education and research, however they did not have the necessary skills to manage the design and the construction of the project. Therefore CQU has appointed your consultancy firm called PPMP20011 consultant to supervise the project and manage all aspects. • Your firm (PPMP20011) is an experienced consultancy firm who provides an in-depth advice to clients on how to proceed within the project constraints. CQU main concerns (limitations) are as follow: I. Time: where this building must be ready before the new academic year II. Quality: The standard of the quality is of high level with the intention to having a prestigious project III. Cost and price certainty: CQU has a strict budget and the project cost should not overruns the project budget. Solid estimate for the project is needed taking all factors into account. During the work, the budge shot be monitored closely and contingency plans put in place for any extraordinary conditions. IV. Preferences for the subprojects are as indicated in the Table: Project/ No. PRIORITY Cost Time Quality Project 1: Main lecture building 3 1 2 Project 2: Computer and engineering Laboratories 1 2 2 Project 3: Conference hall 1 1 3 PPMP20011 Contract and Procurement management Term2 - 2020 Practical Assessment (Two Parts 30% report +10%Peer Assessment) Criteria For Procurement The selection of the right procurement route based on specific requirements is an important part of the successful project. By referring to the knowledge gained in week 1-4, what you need to apply this knowledge and suggest the best procurement route for each project of the above Notes: • You may need to work for each project separately • Important note: You may need to make various assumptions, which is fine. All assumptions need to be listed and justified. Main points to address: These are your TASKS Marks Task Expectations 10 % Understanding and analysis of the case study and applying the concepts of contract and procurement strategies Introduce to the case study whilst explaining the concept of the procurement and contract strategy. Show good level of understanding to the procurement strategies in general, and value for money, in reflection to the case study. (around 100-150 words) 35% 1) Select/recommend the best procurement route (method). 2) You may use various routes to suite the different projects considering the limitations and constraints and the priority in terms? 3) Justify and explain why this could be the best route in line of the 8 points shown 4) DONOT PROVIDE GENERAL TEXT 5) You need to explain each point by reflecting the project requirements in specific You may initially discuss and investigate various procurement routes (minimum 3) Explain advantages and disadvantages of each route Based on your discussion, advantages and disadvantages of the routes, you may select the best route for each project. Show why do you think this is a good route referring to the project constraints, requirements and nature comparing with other routes. Why other routes were excluded? Discuss the routes in line with the following parameters: 1- Time 2- Cost 3- Quality (level of service) 4- Changing orders 5- Complexity 6- Owner capacity and experiences 7- Responsibility and other issues 8- Remember, you need to select separate route for each sub-project. 9- Selecting and discussing routes other than the ones explained in PPMP20011 unit will be graded as ZERO. 10- Make you answers mapped with PPMP20011 unit content. Keep your answer specific and in line with the requirements and project data. (around 600- 800 words) 20% Select the best contract type for this project (Fixed price (lump sum, unit price etc.) Or reimbursement (CPF, CPFF, etc...) What type of contract you recommend (based on the selected route/ project). Again, different contract may be recommended for each project. Why do you think this is a suitable contract from Owner point view? (300-400 words) 20% Budget Breakdown: You may provide budget for one project (Only One Project) • You can refer to any reference/ standards in your estimate • You need to cite the reference. • You can also make your own assumptions • The budget and cost analysis should be for relevant items within the project you are selecting. • Develop a rough cost estimate and budget for ONE project Only • You need to price main items (No more than 5 items) within the project and assign a reasonable estimate. Make valid assumptions. • This needs to reflect both direct and indirect cost (200-300 words) 15% Applying suitable negotiation strategies, particularly BATNA • You may need to be equipped with High quality procurement skills to be able to acquire the various project requirements. • Apply a clear negotiation strategy that can be applied within the project • Show where and when to apply these strategies • What is the constraints from the owner point view? (100-150 words) Notes: 1- The wording count in the Table is a guide, you may use LESS but not more words than specified. 2- Your submission should represent a business report (Not an academic paper) explaining the above requirements in the same order. 3- The submission should address all highlighted tasks and provide enough details Introduction: Project Elements: Important notes: CQU main concerns (limitations) are as follow: Criteria For Procurement Main points to address: These are your TASKS
Answered Same DaySep 02, 2021PPMP20011Central Queensland University

Answer To: Central Queensland University XXXXXXXXXXPPMP20011: Contract & Procurement XXXXXXXXXXmanagement...

Arundhati answered on Sep 03 2021
142 Votes
Contract & Procurement management (Central Queensland University case)
Table of Contents
Understanding and analysis of the case study and applying the concepts of contract and procurement strategies    3
Select/recommend the best procurement route (method)    4
Advantages and disadvantages of each procurement route    6
Selection and justification of best procurement route    6
Selec
t the best contract type for this project    9
Budget Breakdown    10
Applying suitable negotiation strategies, particularly BATNA    11
References    12
Understanding and analysis of the case study and applying the concepts of contract and procurement strategies
The case study is based on CQ University proposal of a project underlined to achieve the developing domestic students’ numbers along with offer an effective university life. The University has already purchased 40 Acers land for constructing main lecture, computer and engineering laboratories and conference hall. Despite of a project size, there are some of the procurement strategies, which could be applied in construction are cost reduction, global sourcing, risk management, total quality management, supplier management and optimization and others. A robust cost reduction and risk management procurement strategy cold minimize limitations, spot savings chances in the CQ University proposal and ensure policy compliance.
Select/recommend the best procurement route (method)
The core need for the procurement route to operate efficiently is for all design works to be finished previously to tender. If this need is met, then the route could provide cost effectiveness post tender, and effective quality assurances. Three main procurement routes that has connection with the current CQ University proposal and construction project are Design and Build Procurement Route, Management Contracting Procurement Route and Construction Management Procurement Route. The Design and build route include construction works and design part under the same contractor. The management contracting route varies in process in which design part is undertaken by external consultant (Alhusban, Danso-Amoako & Gaterell, 2017). The Construction management procurement route construction process starts prior design completion and both include varied parties.
Figure 1: Design and Build Procurement Route
(Source: Nixon & Abraham, 2019)
Figure 2: Management Contracting Procurement Route
(Source: Ferme, Zuo & Rameezdeen, 2018)
Figure 3: Construction Management Procurement Route
(Source: Tiwari, Chan & Mubarak, 2018)
Advantages and disadvantages of each procurement route
    Procurement routes
    Advantages
    Disadvantages
    Design and Build Procurement Route
    Proposals for project is shortlisted based on cost and quality of design (Nixon & Abraham, 2019).
    Risk of developing cost lies with the contractor
    Management Contracting Procurement Route
    Project duration is usually short
    Designing risks generally lie on the part of project owner as accountable for the design (Nixon & Abraham, 2019)
    Construction Management Procurement Route
    Client could appoint construction manager base on fixed fees (Nixon & Abraham, 2019)
    Risks are there related to project completion in given time
Table 1: Advantages and Disadvantages of each procurement route
(Source: Created by the Learner)
Selection and justification of best procurement route
As per the project priorities and resource capabilities of CQ university, the best procurement route would be Design and Build Procurement Route Design and Build Procurement Route. The design and build procurement route are effective for this project as the timeline needed to complete the three projects will be known with certainty. Cost needed for the project will also be projected before design. Owner could be...