Your firm has been asked to do a preliminary study of the feasibility of a new A /O™ BPR wastewater treatment plant for Pittsburgh. Begin the design of the complete-mix BOD removal and nitrification stage. As a first step determine the SRT and volume of tank required for nitrification using the following design data:
Influent data after primary settling
Design flow rate = 35,500 m3
/d
BOD = 200 mg/L
bCOD = 320 mg/L
rbCOD = 60 mg/L
Total Kjeldahl nitrogen (TKN) = 45 mg/L
NH -N = 35 mg/L
Soluble phosphorus = 7 g/m3
Total suspended solids (TSS) = 75 mg/L
Volatile suspended solids (VSS) = 65 mg/L
Biodegradable volatile suspended solids = 40 mg/L
Minimum sustained temperature = 15°C
pH = 7.0
Alkalinity = 220 mg/L as CaCO
Effluent discharge standards
bCOD ≤ 20 mg/L
NH3
-N ≤ 1.0 mg/L
NO3
-N ≤ 10 mg/L
TSS ≤ 10 mg/L
Total phosphorus ≤ 2.0 mg/L
Assume DO for aeration tank nitrification = 2.0 mg/L; MLSS = 3,500 mg/L, MLVSS = (0.8) MLSS, NO = 80% of TKN, and RAS = 0.54(Q).