You$run$a$small$software$company$that$has$been$contracted$to$provide$a$product.$$Given$all$the$ information$below,$perform$an$earned$value$analysis$at$the$end$of$week$8....

1 answer below »
You$run$a$small$software$company$that$has$been$contracted$to$provide$a$product.$$Given$all$the$ information$below,$perform$an$earned$value$analysis$at$the$end$of$week$8. Calculate$the$following$values$for$week$8 Earned$Value Planned$Value Actual$Cost Cost$Variance Schedule$Variance Cost$Performance$Index Schedule$Performance$Index Estimate$at$Completion Estimated$Time$to$Complete Generate$a$graph$that$shows$the$Actual$Cost,$Earned$Value,$and$Planned$Value$for$weeks$1G8.$ Will$this$project$be$completed$on$time? Will$this$project$be$completed$within$the$budget? Project&Estimates Week&1: The$project$gets$started$on$time,$Joe$puts$in$4$hours$of$work$to$complete$the$initiation$phase Week&2: Mary$starts$the$project$specifications$but$is$held$up$by$another$project$halfway$through. Week&3: Mary$completes$the$second$half$of$the$project$specifications$in$6$hours. Chris$purchases$the$developer$machines$for$$4800$and$the$development$server$for$$6000,$it$takes$him$2$ hours$to$research$and$purchase$them. Week&4: Pete$and$Joe$complete$the$Design$Output,$doing$50%$of$the$work$each$in$a$total$of$8$hours. Week&5: Chris$spends$two$hours$trying$to$find$a$good$production$server. Joe$is$out$sick.$Pete$puts$10$hours$into$the$test$planning. Week&6: Joe$finishes$up$the$test$planning$in$8$hours. Mary$starts$on$the$code$and$puts$in$20$hours. Week&7: Mary$is$out$sick,$nothing$happens. Week&8: Chris$finally$find$a$deal$on$a$production$server$for$$10,000 Mary$is$75%$done$with$the$code$after$putting$in$another$6$hours. Joe$completes$15%$of$the$unit$testing$in$4$hours$time.
Answered Same DayDec 07, 2021

Answer To: You$run$a$small$software$company$that$has$been$contracted$to$provide$a$product.$$Given$all$the$...

Riddhi answered on Dec 08 2021
136 Votes
Earned Value
Earned Value is the value at the stage of completion at this stage. The value shall be the budgeted cost which was originally decided at each stage of completion of work.
Earned Value = % Completion Actu
al x Task Budget
In this case earned value shall be Budgeted hours required to complete the work for the % of work completed plus Budgeted Hardware Cost
Earned Value = Hardware Cost + Manpower Cost
Earned Value = $25,000 + $2,092.685
Earned Value = $27,092.685
    Budgeted Hours
    Joe
    Mary
    Chris
    Pete
    Total
    Week1
    3
     
     
     
    3
    Week2
     
    8
     
     
    8
    Week3
     
     
    2
     
    2
    Week4
     
     
     
     
    0
    Week5
    5
     
     
    5
    10
    Week6
    14
    30
     
     
    44
    Week7
     
    
     
     
    0
    Week8
    1.05
    
     
     
    1.05
     
     
     
     
     
     
    Hours
    23.05
    38
    2
    5
    68.05
    Hourly Rate
    27.5
    34
    44.28
    15.65
     
     
     
     
     
     
     
    Total Cost of Hours
    633.875
    1292
    88.56
    78.25
    2092.685
    Budgeted Cost
    Cost
    Development Cost
    $5,000
    Development Server
    $8,000
    Production Server
    $12,000
     
     
    Total cost
    $25,000
Planned Value
Planned Value is the value that has been planned for at the current stage of completion. It is the planned or scheduled time or value that should have been estimated which is equivalent to the budget assigned to the project.
Planned Value = % Complete planned x task budget
Planned value shall be the cost of completing the work till the stage of unit test and completing writing codes and the manhours for the same are as below plus hardware Cost
Planned Value = Budgeted Manpower Cost + Hardware Cost
Planned Value = $2,596.31 + $25,000
Planned Value = $27,596.31
    Budgeted Hours
    Joe
    Mary
    Chris
    Pete
    Total
    Week1
    3
     
     
     
    3
    Week2
     
    8
     
     
    8
    Week3
     
     
    2
     
    2
    Week4
     
     
     
     
    0
    Week5
    5
     
     
    5
    10
    Week6
    14
    40
     
     
    54
    Week7
     
    
     
     
    0
    Week8
    7
    
     
     
    7
     
     
     
     
     
     
    Hours
    29
    48
    2
    5
    84
    Hourly Rate
    27.5
    34
    44.28
    15.65
     
     
     
     
     
     
     
    Total Cost of Hours
    797.5
    1632
    88.56
    78.25
    2596.31
    Budgeted...