A total of 1000 units of a certain product must be completed by the end of the current week. It is now late Monday afternoon, so only four days (8-hour shifts) are left. The standard time for producing each unit of the product (all manual operations) is 11.65 min. How many workers will be required to complete this production order if it is assumed that worker efficiency will be 115%