If a company assigns factory labor to production at a cost of $84,000 when standard cost is $80,000, it will Group of answer choices credit Labor Price Variance for $4,000. credit Labor Quantity...


If a company assigns factory labor to production at a cost of $84,000 when standard cost is $80,000, it will

Group of answer choices

credit Labor Price Variance for $4,000.



credit Labor Quantity Variance for $4,000.



debit Labor Price Variance for $4,000.



debit Labor Quantity Variance for $4,000.