Answer To: PLease see the attached document
Khushboo answered on Feb 12 2023
PA4-3
Direct material cost per unit 37 70
Direct labor cost per unit 18 37
Sales price per unit 357 584
Expected production per month 750 340
Monthly overhead 166000
Setup costs 76950
Quality control 52650
Maintenance 36400
166000
No of setups 37 58 95
No of inspections 340 310 650
No. of machine hours 1200 1400 2600
Solution 1
Overhead assigned
Home model 76,615
Work model 89,385
Total overhead cost 166,000
Solution 2
Home Work
Unit cost 157.15 369.90
Solution 3
Home Work
Gross margin 199.85 214.10
Solution 4
Setup costs No of setups 810.00
Quality control No of inspections 81.00
Maintenance No. of machine...