SBM4201 System Analysis and Design XXXXXXXXXXPage 1 of 2 SBM4201 System Analysis and Design Semester 1, 2018 Portfolio Assessment Portfolio No.: XXXXXXXXXX Group/individual: Individual Assignment...

1 answer below »
5 portfolios


SBM4201 System Analysis and Design Page 1 of 2 SBM4201 System Analysis and Design Semester 1, 2018 Portfolio Assessment Portfolio No.: 1 Group/individual: Individual Assignment Weighting: 10% Question one: Allhomes Company Case Study The IT department at the Allhomes company has received the approval to add new position of systems analyst. Your role is to support the set up the hiring timetable and tasks. After discussion with a number of employee in the department, you identified the tasks and the order in which they have to be performed as follows: First, review the applications (2 days). Then start three tasks: notify the IT team (1 days) and set up an interview schedule (5 days). When the team has been notified and the conference room reserves, prepare a set of interview questions (2 days). When the questions are ready, and the interview schedule has been developed, conduct the interviews (5days). After the interviews are done, meet with the hiring committee to select a candidate (1 day). Tasks: 1. Prepare a work breakdown structure explaining task, durations, and predecessor task. 2. Calculate the start and finish date for each task and determine the critical path. Question two: iTech Company Case Study The HR department at the iTech company offers a job position to Kim Jones. She will start the new job after three weeks. As an IT department member, you were asked to set up an orientation for her, including meeting with human resources, users, and the IT team. Tour at the company needs also to be organized. You suggested the following schedule: First, Kim have to meet with the human resources to learn about the company benefits and policies (3 hours). After finishing the meeting, she has to handle three tasks at once: she could tour the company offices (4 hours), meet with the users (3 hours), and work on the necessary paperwork (2 hours). Then, after meeting the IT manager and with all the paperwork completed, she would meet with the entire IT team for a brief introduction (1 hours). SBM4201 System Analysis and Design Page 2 of 2 Tasks: 1. Prepare a work breakdown structure explaining task, durations, and predecessor task. 2. Calculate the start and finish date for each task and determine the critical path. SBM4201 System Analysis and Design Page 1 of 1 SBM4201 System Analysis and Design Semester 1, 2018 Portfolio Assessment Portfolio No.: 2 Group/individual: Individual Assignment Question one: Course Registration Case Study An educational institute has a course registration system. The student access the institute website to check the course schedule and register a course. Once the student pays the course fees, the system provides the fee statement. At the student service department, the registrar prepared the course schedule and updates courses information as required. The cashier can access the payment system to check the student’s payments and courses registration process. Instructors and tutors can view the number of students registered in any course. 1. List possible entities in the registration system, including their attributes. 2. Identify possible use cases and actors. 3. Draw the use case diagram that explain the students process of student registration. You may need to make some assumptions with the required justifications SBM4201 System Analysis and Design Page 1 of 1 SBM4201 System Analysis and Design Semester 1, 2018 Portfolio Assessment Portfolio No.: 4 Group/individual: Individual Assignment Protfolio-4: Poster The purpose of a poster is to provide a visual summary of student’s ideas that outlines key message or argument as well as the key points or proposal. A poster uses very few words with appropriate visuals and graphics. Task Specifications In Protfolio-4, the student have to prepare a poster to present his/her message in the topic of Data Modelling. The poster should have clear structure and layout to support that message. The poster has to consider the followings main topics such as: - The benefit of data modelling in system analysis - Types of data modelling in systems analysis - Conceptual, Logical and Physical models - The ways of transition from one data model to another. - Methods of data analysis. - Case study examples illustrating data modelling. Prepare a poster to demonstrate your research, analysis or ideas in range of visual techniques such as illustrations, schematic diagrams, arrows or flow charts and cues such as bullet points, colour and design. Poster Development  Use any application software you are familiar with in the development of your poster, such as Microsoft Word, Microsoft Power Point, Microsoft Publisher, Adobe Photoshop, or any other software.  Set your poster page size to A4 and develop your poster. SBM4201 System Analysis and Design Page 1 of 1 SBM4201 System Analysis and Design Semester 1, 2018 Portfolio Assessment Portfolio No.: 3 Group/individual: Individual Assignment Weighting: 10% Question one: Case Study High Education College (HEC) is an educational institute provides different courses in information technology. The institute wants to develop and deploy new Online Learning System (OLS). The OLS required to install and configure email, web, database and management servers to provide the required services such as emails for staff and students, web page and database management system. In addition, the networking infrastructure must be established to provide communication and networking facilities with the required security and system availability. Different types of network devices and support servers including networking switches and routers must be installed and configured with all the required cabling services. Security devices and backup services are required to improve the system performance. The institute wants to develop two online learning systems, Undergraduate Learning System (ULS) and Postgraduate Learning System (PLS). The software developers at the IT department assigned the task of developing both learning systems from scratch within 1 year and 4 months. Task: The Systems Development Life Cycle (SDLC) identifies all the activities required to build, launch, and maintain an information system. Discuss the six core processes of the SDLC required to develop the OLS project for the HEC. You have to provide detailed information regarding each core processing activity. Your answer should consider Work Break Down (WBS), sequence of activities and the dependencies of those activities. In addition, you have to used modeling, use cases and other required techniques and tools with justification. SBM4201 System Analysis and Design Page 1 of 1 SBM4201 System Analysis and Design Semester 1, 2018 Portfolio Assessment Portfolio No.: 5 Group/individual: Individual Assignment Weighting: 10% Question one: ABC Company Case Study You work as system analyst at ABC company, your role focus on testing web-based system that involved different set of tools and technique. Your manger wants you to offer consulting services specifically in testing the performance, integrity, efficiency, and security of Internet-based systems. Your manager wants you to identify various website testing tools that currently are available, then use these tools
Answered Same DayMay 03, 2020

Answer To: SBM4201 System Analysis and Design XXXXXXXXXXPage 1 of 2 SBM4201 System Analysis and Design Semester...

Amit answered on May 10 2020
138 Votes
Title of the assignment:
Student’s name:
Professor’s name:
Course title:
Date:
Table of Contents
PORTFOLIO-1    3
1.    Possible entities and related attributes of course registration system    3
2.    Possible use cases and related actors    3
3.    Use case diagram for student registration process    4
4.    References:    5
PORTFOLIO-2    5
1.    Task 1: WBS development and calculation of critical path    5
2.    Task 2: WBS develop
ment and calculation of critical path    7
PORTFOLIO-3    8
1.    SDLC steps for online learning project of HEC    8
2.    WBS for online learning project of HEC    9
3.    Performed activities with possible dependencies    10
4.    Use case for justification    10
5.    References:    11
PORTFOLIO-4    11
1.    Poster of data modeling    11
PORTFOLIO-5    13
1.    Screen shot of web search    13
2.    Eggplant Functional tool    13
3.    iMacros tool of web testing    14
4.    OpenTest tool of web testing    15
5.    Ranorex Studio tool of web testing    15
PORTFOLIO-1
1. Possible entities and related attributes of course registration system
The given case of student registration system to select any course by paying specific fee to cashier has different entities and related possible attributes [Dennis et al, 2015]. The entities with possible attributes of given system are listed below:
· Student(studentIDNo, nameOfStudent, courseOfStudent, stdAddress, stdContactNo)
· Instructor(IDNoOfInstaructor, nameOfInstructor, speciflizationOfInstructor)
· Course(IDNoOfCourse, nameOfSelectedCourse, feeOfSelectedCourse,enrolledStudents)
· Fee(amount, receiptIDNo, feeReceipt)
· Cashier(IDNoOfCashier, statusOfPayment)
2. Possible use cases and related actors
The possible use cases of given system with related actors are listed below [Montgomery, 2017]:
1. Registration to specific course(Student, system itself)
2. Fee submission for course(Cashier, student)
3. Instructor allocation( Instructor, and student)
3. Use case diagram for student registration process
The developed of complete process in single diagram is very critical task. The developed Use case Diagram for desired system is as provided below [Wasson, 2015]:
Explanation:
1. The desired course is applied by student.
2. The availability of selected course module checked by the system.
3. The predefined fee is deposited by student.
4. The total enrolled numbers of students are checked by allocated instructor.
5. The fee status is verified by cashier and course updating is performed.
4. References:
Dennis, A., Wixom, B. H., & Tegarden, D. (2015). Systems analysis and design: An object-oriented approach with UML. John wiley & sons.
Montgomery, D. C. (2017). Design and analysis of experiments. John wiley & sons.
Wasson, C. S. (2015). System engineering analysis, design, and development: Concepts, principles, and practices. John Wiley & Sons.
PORTFOLIO-2
1. Task 1: WBS development and calculation of critical path
1)
The project development activities defined by any organization to make easily controllable sections are called WBS. The developed WBS for given organization’s hiring process is provided below:
    Task no.
    Description
    Required days to complete task
    Predecessor task no.
    1.
    Make reviews for submitted applications.
    2
    -
    2.
    Notify to all team members.
    2
    1
    3.
    Reserve conference room for completing interview process.
    1
    1
    4.
    Make interview schedule.
    5
    1
    5.
    Develop question set which will be asked in interview.
    2
    2,3
    6.
    Conduct the interview.
    5
    4,5
    7.
    Make a meeting with hiring committee of Allhomes Company to select candidates.
    1
    6
2)
The desired calculations of critical path with start and finish date of allocated tasks is provided below:
    Task no.
    Description
    Start date
    Finish date
    1.
    Make reviews for submitted applications.
    0
    2
    2.
    Notify to all team members.
    2
    4
    3.
    Reserve conference room for completing interview process.
    2
    3
    4.
    Make interview schedule.
    2
    7
    5.
    Develop question set which will be asked in interview.
    4
    6
    6.
    Conduct the interview.
    7
    12
    7.
    Make a meeting with hiring committee of...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here