- This assignment is based on surveying and engineering construction.- Modules, Tutorials and assignment are all in the zip file-I have been on this website once before and was impressed by the marks i received for a previous engineering assignment. This is why i came back.-If there are any questions, feel free to ask.


ASSIGNMENT + MODULES&TUTORIALS/Assignments 2020 SVY2303 (2).pdf SVY2303 Introductory book Page 1 SVY2303 Construction surveying SVY2303 Introductory book Page 2 Course assessment Assignment extension policy The penalty for late submissions of assignment work is documented in the USQ Assessment Procedure link below, in practice penalty will be applied at up to 10% per day late to a maximum of 2 weeks. This penalty may be waived in part or in total where: ● failure to meet the due date for submission of assignment work was due to ill-health or other reasons beyond your control, such as excessive or exceptional work commitments and can be substantiated by documentary evidence such as a medical certificate or a signed statement from your employer. ● assignment extension applications must be lodged prior to the due date of the assessment ● Students should refer to the USQ Assessment Procedure: http://policy.usq.edu.au/documents.php?id=14749PL (point 4.2.4) Objectives assessed in this course Module Objectives 1 2 3 4 5 6 7 8 9 10 11 Assignment #1 ✓ ✓ ✓ ✓ Assignment #2 ✓ ✓ ✓ ✓ Assignment #3 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ Course Objectives 1 2 3 4 Assignment #1 ✓ ✓ ✓ Assignment #2 ✓ ✓ ✓ Assignment #3 ✓ ✓ ✓ Past examination Past examinations for this course can be found on the Studydesk. http://policy.usq.edu.au/documents.php?id=14749PL SVY2303 Introductory book Page 3 Assignment 1 Due date: 24 August 2020 Value: This assessment carries 200 of the 1000 total marks for this course (20% of total weighting) Question 1 (60 marks) a. Activity Duration Precedents A-Start 0 B 3 A C 3 A D 2 A E 4 BC F 8 D G 9 F H 2 EG I 3 G J 6 F K 3 J L 4 I M 3 KL N 1 M O 4 K P-End 0 HNO Draw a Gantt Bar chart representing the above events, depicting: activity and duration, total float, critical path and duration. (20 marks) b. List the most appropriate type of contract and discuss the reasons for your conclusion for the following tenders: (i) The supply of three (3) robotic total stations plus specified associated equipment; (ii) The supply and delivery of cadastral survey pegs and stakes to a large residential subdivision at a specified location - approximately 2000 to 3000 units for each item. ((i,ii) List 8 marks, Discussion 12 marks) Marking scheme for 1(a): Activities/duration Chart 50%, Float 25%, Critical path/duration 25%. Marking scheme for 1(b): List 25%, Explanation 75% SVY2303 Introductory book Page 4 Question 2 (70 marks) a. The following natural surface levels were taken along the proposed centre line of a road: Chainage/meterage RL 600 620 640 660 680 700 720 740 760 780 800 30 30.5 31 31 32 33 33 32.5 32.2 32 31 An equal tangent parabolic vertical summit curve is to be placed between two successive design formation grades of +3.0% and -2.0% which meet at a point 700m at a reduced level of 33.2 m. The length of the curve is 200 m. Compute and tabulate: i. the calculated RL’s of the chainages/meterage along the tangents; (5 marks) ii. the reduced levels of the design surface; (10 marks) iii. the cut(-ve) or fill(+ve) required at each peg at the centre line. (5 marks) b. The centre-line of two railway culverts is required to be set-out from the start of a transition curve, curving to the right. Calculate the deflection angle and chord from the start of the transition curve using the rigorous ideal transition curve formulae, using the following data: Intersection angle = 20o19'50" Radius = 350m Transition length = 50 m Start point (TS) of transitioned curve = 565 m (i) Chainage/meterage of culvert one = 610 m (ii) Chainage/meterage of culvert two = 680 m (i 10 marks, ii 20 marks) c. A surveyor when placing a fill situation catch point mark for batter marking, measures the modelled catch point by the following data and given information: Height of collimation of level = 87.0 m Design centre-line level = 86.15 m SVY2303 Introductory book Page 5 Distance from the design centre-line to edge of shoulder = 5.0 m Pavement crossfall from the design centre-line = -3% Shoulder batter (-ve for fill situation) = -1: 0.5 (horizontal to vertical) or -2: 1 Natural surface staff reading for catch point = 2.43m, taken at the 8m modelled offset from the centre-line as read off the construction tables. Calculate if the catch point is in the correct modelled position, and if not, what would be a suggested shift, assuming the ground is level, apply a check to your solution. (20 marks) Question 2 marking schemes: Calculations: 75%, Check: 25%, fully document your answers. Question 3 (70 marks) a. Robert from River Adventures runs a white-water rafting company and tells you that the Clearwater River varies in height over the season by about 5 metres and this affects the raft speed. Based on the information below. (30 marks) Roughness coefficient = 0.025 Hydraulic gradient = 0.016m/m Acceleration due to gravity = 9.8m/s2 Calculate the (i) hydraulic radius and velocity of flow by Manning’s Formula and (ii) rate of flow per hour for both the high water and low water marks. (i 5 marks, ii 10 marks, for each water mark) 6m SVY2303 Introductory book Page 6 b. The top of a pile requires final placement at E 100.8, N 200.6 and RL 50m (say for bridge/wharf/jetty construction). The pile is angled away from the centre-line along the line of the piles, into the sub-surface at a +10 angle off normal. The bridge centre-line has a bearing of 20 and the required line of piles to the left of the centre-line has a bearing of 290. A measurement to the current position of the pile top has been reduced to be at E 101.5, N 200.1 and RL 55.9m. Calculate the required movement of the pile top, so as to be positioned to commence driving at RL 55.9m, along the line of skew. See plan and elevation views below. (30 marks) c. A flight of levels is run from a Bench Mark of R.L. as per the table below and the following readings obtained: (Booked down the page) B/S I/S F/S RL HI (coll.) Comment 1.34 1.65 1.11 0.86 0.496 0.985 1.978 1.121 1.230 86.40 BM1 CP1 CP2 CP3 CP4 At CP4 position of the level, six height pegs at 20 metre intervals (100m in total) are to be set out at a falling grade of 1 in 420. The first peg (i.e. 00) has a design level of 86.20m. Calculate the grade levels and staff readings required for the top of each peg using the Height of collimation booking method and enter the results in level book form. (10 marks) Question 3 marking schemes: Calculations 100%, fully document your answers. 3 0 ° c/ l 300° line of piles and measured position RL 50m ce n tr el in e
Answered Same DayJul 30, 2021

Answer To: ASSIGNMENT + MODULES&TUTORIALS/Assignments 2020 SVY XXXXXXXXXXpdf SVY XXXXXXXXXXIntroductory book...

Ishwar answered on Aug 22 2021
142 Votes
Construction surveying
Student Name
University
Assignment 1.a
Gantt chart:
The following is provides “network diagram” to obtain critical path o
f complete procedure.
As shown in above diagram, the “RED” highlighted is critical path of complete procedure.
a. Critical path = ADFGI L M N P
Duration = 0 + 2 + 8 + 9 +3 + 4 +3 +1 = 30
Total float =duration of critical path –duration of non-critical path
a. Non-critical path = AB E H->P = 0+ 3 +4+0 = 7
b. Non-critical path = ACEH P = 0 + 3+4+2+0 = 9
c. Non-critical path = ADFJK O M N P = 0+2+8+6+3+4+3+1+0 = 27
d. Non-critical path = ADFGILMNP = 0+2+8+9+3+4+4+3+1+0 = 34
e. Non-critical path = ADFGH P = 0+2+8+2+0 = 12
1. Total float (a) = 30-7 = 23 days
2. Total float (b) = 30-9 = 21 days
3. Total float (c) = 30 -27 = 3 days
4. Total float (d) = 30 – 34 = -4 days
5. Total float (e) = 30-12 = 18 days
Assignment 1.b
1.
The most common used contracts are:
a. Lump Sum contracts
b. Schedule of rates contracts
Management contracts:
As per provided requirement, the management contracts and tendering procedure is suitable for multiple activities. In this case, the supply and delivery of cadastral survey pegs and stakes to the large residential subdivision at the specific location. In this case, the project includes design, project planning and management for supply and delivery of cadastral survey pegs. The project manager will undertaking the work which must be carried out for specific function either within own...