A process makes two products, A and B, and operates 5 days per week, 8 hoursper day. Demand for the two products for the next week is as follows:Day 1: A: 4; B: 6Day 2: A: 5; B: 5Day 3: A: 6; B: 4Day 4: A: 7; B: 3Day 5: A: 3; B: 7What is the takt time of the process? What would a level production schedule look like?