Page | 1 Asia Pacific International College Pty Ltd. Trading as Asia Pacific International College 55 Regent Street, Chippendale, Sydney 2008: XXXXXXXXXX PRV12007; CRICOS 03048D Unit Code and Title:...

1 answer below »
can you please make this assessment on Sydney CBD fright project


Page | 1 Asia Pacific International College Pty Ltd. Trading as Asia Pacific International College 55 Regent Street, Chippendale, Sydney 2008: 02-9318 8111 PRV12007; CRICOS 03048D Unit Code and Title: SBM1201 Project Scope, Time and Cost Management Assessment 3: Unit Project-Part B (Group) Due date: Week 10 Group/individual: Group Word count / Time provided: 3000 words Weighting: 30% Unit Learning Outcomes: ULO-1, ULO-2, ULO-3, ULO-4 Course Learning Outcomes: CLO-1, CLO-3, CLO-4, CLO-5, CLO-6, CLO-8, CLO-9 Graduate Attributes: GA-K2, GA-S1, GA-S3, GA-AKS3, GA-AKS4, GA-AKS5, GA-AKS6 Assessment Details: Continue working on the selected project case, this assessment is designed to assess your technical skills in planning and communicating a project effectively. You required to continue working with your group on the selected project and develop and write schedule management plan that includes identify processes, tools and techniques to be used and document to be developed as per your client’s requirements, define activities (activity list, proper activity logic, activities identification), milestones list, activities sequence, relationships (F_S, S_S, S_F, F_F), Lags, leading times, project network and critical path(s), estimating activity duration (basics of estimation, durations, resources estimation and allocation), identifying roles and responsibilities in scheduling, and monitoring and controlling schedule (EVA relevant to project schedule) Just description of the methods and tools. Using your MS project skills, you are required to develop MS project report of schedule plan, and resources plan (sheet and allocation for each activity) and develop schedule baseline. You also require to develop and write project cost management plan that includes: plan cost management (identify processes, tools and techniques to be used and project documents to be developed as per your client’s requirements), define cost elements (labour, material, variable cost), identify types of cost (direct, indirect, fixed, variable), determine the estimating method (s): (top-down, bottom-up), use estimating techniques (analogous, parametric, three-point method) to estimate budget (creation): establish time-phased budget, provide a discussion on monitoring and controlling cost (EVA relevant to project cost including forecasting and variances), and establish a cost baseline. For successful completion of this assessment, you should meet with your group regularly (at least once a week face to face or via Zoom meeting). you require to study the material provided (lecture slides, tutorials, and reading materials), engage in the unit’s activities, and in the discussion forums. The prescribed textbook is the main reference along with the recommended reading material. Groups expected to discuss their work with lecturer and to seek support. In completing this assessment successfully, you will be able to effectively to write and communicate project scope and schedule plan, which will help in achieving ULO-1, ULO-3, and ULO-4. Assessment-3 Brief Page | 2 Asia Pacific International College Pty Ltd. Trading as Asia Pacific International College 55 Regent Street, Chippendale, Sydney 2008: 02-9318 8111 PRV12007; CRICOS 03048D Marking Criteria and Rubric: The assessment will be marked out of 100 and will be weighted 30% of the total unit mark Marking Criteria Not satisfactory (0-49%) of the criterion mark) Satisfactory (50-64%) of the criterion mark Good (65-74%) of the criterion mark Very Good (75-84%) of the criterion mark Excellent (85-100%) of the criterion mark written communication skills (10 marks) Organising Grammar Spelling Clarity Format Using of charts and graphs as per project management best practices Lacks evidence of skills relevant to communicate (writing) in project environment Evidence of basic skills of communicating (writing) in project environment Has given a factual and/or conceptual skill base in communication (writing) in project environment Has good skills in communicating (writing) a project report Has excellent skills in communicating (writing) in project environment Project Schedule (35 marks) Plan schedule management (identify processes, tools and techniques to be used and document to be developed as per your client’s requirements) Define activities (activity list, proper activity logic, activities identification) Milestones list Activities Sequence Relationships (F_S, S_S, S_F, F_F) Lags, leading times Project network and critical path(s) Estimating activity duration (basics of estimation, durations, resources estimation and allocation) Roles and responsibilities in scheduling Monitoring and Controlling Schule (EVA relevant to project schedule) Just description of the methods and tools Schedule baseline Lacks evidence of knowledge relevant to project schedule management Evidence of basic knowledge and skills of project schedule management Has given a factual and/or conceptual knowledge and skills base in schedule management. But have many missing main components of project schedule management plan such as activities relationships, sequences…etc. Reasonable knowledge and skills of developing project schedule management plan, but one or more main component is missing Has excellent knowledge and skills of developing a project schedule management plan, including all project schedule management processes from the plan, to identify activities, estimate durations, setting up their sequences, building network, assigning resources, defining roles and responsibilities and in monitoring and controlling project schedule Project Cost Management (35 marks) Plan cost management (identify processes, tools and Lacks evidence of skills relevant to develop and communicate project cost management plan, identify project cost Evidence of basic skills of developing and communicating project cost management plan, identify project cost Has given a factual and/or conceptual skill base in developing and communicating project cost Reasonable knowledge and skills of developing and communicating project cost management plan, Has excellent knowledge and skills of developing a project cost management plan, including all project Page | 3 Asia Pacific International College Pty Ltd. Trading as Asia Pacific International College 55 Regent Street, Chippendale, Sydney 2008: 02-9318 8111 PRV12007; CRICOS 03048D techniques to be used and project documents to be developed as per your client’s requirements) Cost elements (labour, material, variable cost) Types of cost (direct, indirect, fixed, variable) Estimating method (s): top-down, bottom-up Estimating techniques (analogous, parametric, three- point method) Contingencies and management reserves Budget (creation): time-phased budget Monitoring and Controlling Cost (EVA relevant to project cost including forecasting and variances) only description Cost baseline types, methods of estimating costs, estimating costs of the selected project, monitoring and controlling costs. types, methods of estimating costs, estimating costs of the selected project, monitoring and controlling costs. management plan, identify project cost types, methods of estimating costs, estimating costs of the selected project, monitoring and controlling costs. But missing many main components identify project cost types, methods of estimating costs, estimating costs of the selected project, monitoring and controlling costs. But missing one or more main component cost management processes from planning cost management, identifying cost types, applying estimating methods, creating cost baseline and using tools ad techniques for monitoring and controlling project cost MS project report of the cost table EVA report (charts and tables) (20 marks) Lacks evidence of knowledge relevant to use MS project to plan and communicate the project schedule and cost and to communicate project progress reports (EVA, forecasting and variances) via MS project Evidence of basic knowledge and skills of using MS project to plan and communicate the project schedule and cost and to communicate project progress reports (EVA, forecasting and variances) via MS project Has given a factual and/or conceptual knowledge and skills base in using MS project for developing schedule and cost management plan and progress reports. But the MS project report is missing many main components Reasonable knowledge and skills of in using MS project for developing schedule and cost management plan and progress reports. But the MS project report is missing many main components, but one or more main component is missing Has excellent knowledge and skills of developing a project schedule and cost management plan and developing project progress reports (EVA, forecasting and variances) via MS project
Answered Same DayApr 21, 2021SBM1201

Answer To: Page | 1 Asia Pacific International College Pty Ltd. Trading as Asia Pacific International College...

Amar answered on Apr 27 2021
136 Votes
1
Running Header: Assessment 3 – Unit Project Part B
2
Assessment 3 – Unit Project Part B
Assessment 3 – Unit Project Part B
Table of Contents
1.    Project Background    3
2.    Schedule Management Plan    3
2.1.    Process / Tools / Techniques Identification    3
2.2.    Detailed Task Breakdown    4
2.3.    Planned Project Schedule    6
2.4.    Project Milestones    9
2.5.    Activity Sequences / Gantt Chart with Critical Path    10
2.6.    Network Diagram    11
2.7.    Resource Planning    12
3.    Project Budget    16
3.1.    Cost Elements, Cost Types, and Cost Estimations    16
3.2.    Time-phased Budget & Cost Baseline    17
4.    Earned Value Analysis – Schedule / Budget Controls & Monitoring    20
5.    Conclusion    22
References    23
Project Background
This project is being undertaken for delivering growth with respect to the domestic business situation concerning Sydney central business district (“CBD”). The ob
jective of this project shall be to connect various stations that are located across Kingsford, Randwick, central, and George street by way of newer underground based rail line. In effect, the project deliverables encompasses the development of new rail line which connects CBD as well as southeast, enhancement of ferry services already existing along Barangaroo wharf, and building roads to help cycle riders in avoiding issues pertaining to transportation congestion. The project shall be highly beneficial with respect to both individuals as well as business organizations and ultimately benefit the overall economy.
This report which forms part of the project planning documentation, presents the detailed schedule management plan as well as the cost management plan.
Schedule Management Plan
1.1. Process / Tools / Techniques Identification
The planning of the schedule management involved the process to establish the affiliated policies, suitable procedures, as well as the documentation to plan, develop, manage, execute, as well as to control the schedule of a project (Kerzner and Kerzner 2017; Larson and Gray 2017; Fleming and Koppelman 2016). The primary benefit concerning the said process shall be that it offers guidance as well as direction over the ways in which the project schedule shall be suitably managed all through the course of a project (Kerzner and Kerzner 2017; Larson and Gray 2017; Fleming and Koppelman 2016). The said process, while it can be undertaken immediately all at one or else during pre-defined points over the project course, has been undertaken all at once in this planning stage (Kerzner and Kerzner 2017; Larson and Gray 2017; Fleming and Koppelman 2016). The techniques / tools employed to undertake the same entailed expert judgment, data analysis, and team meetings (Kerzner and Kerzner 2017; Larson and Gray 2017; Fleming and Koppelman 2016).
1.2. Detailed Task Breakdown
    LEVEL 0
    LEVEL 1
    LEVEL 2
    LEVEL 3
    Sydney CBD Freight Project
     
     
     
     
    Project initiation
     
     
     
     
    Consult with Stakeholder
     
     
     
     
    Finalizing / Approving of the Project Charter
     
     
     
    Project Team Set-up
     
     
     
    Approval for Project Initiation
     
     
    Gather Requirements and Budget
     
     
     
     
    Preliminary Project Research
     
     
     
    Data Collection & Analysis
     
     
     
    Project Feasibility Assessment
     
     
     
    Fund Planning
     
     
     
    Fund Sourcing Approvals
     
     
    Carry out cost benefit
     
     
    Project planning
     
     
     
     
    Consult with project managers
     
     
     
     
    Project Method Identification
     
     
     
    Project Organization, Structure, and reporting Structure Finalization
     
     
    Identify scope
     
     
     
     
    Scope / Schedule / Budget Planning
     
     
     
    Quality Planning
     
     
     
    Risk Planning
     
     
     
    Documentation
     
     
    Communication plan
     
     
    Project execution
     
     
     
     
    Allocating money
     
     
     
    Identify resource
     
     
     
     
    Resource Planning
     
     
     
    Material Resource Identification
     
     
     
    Procurement Planning
     
     
     
    Vendor / Supplier Negotiation
     
     
     
    Contract Negotiation, Sign-off & Payments
     
     
     
    Receipt of Materials
     
     
     
    Quality Checks
     
     
     
    Resource Allocation
     
     
    Construction
     
     
     
     
    Phase 1 Construction
     
     
     
    Quality Review & Approval of Phase 1 Delivery
     
     
     
    Phase 2 Construction
     
     
     
    Quality Review & Approval of Phase 2 Delivery
     
     
     
    Phase 3 Construction
     
     
     
    Quality Review & Approval of Phase 3 Delivery
     
     
     
    Construction Process Closure
     
     
     
    Review & Approvals
     
    Project control
     
     
     
     
    Recruitment
     
     
     
    Testing
     
     
     
    Allocating responsibilities
     
     
    Project closure
     
     
     
     
    Project review
     
     
     
    Analyse outcomes
     
     
     
    Compare estimation
     
1.3. Planned Project Schedule
    TASK REF #
    TASK LIST
    DURATION
    START DATE
    END DATE
    PREDECESSOR
    1
    Sydney CBD Freight Project
    165 days
    01/05/19 8:00
    17/12/19 17:00
     
    2
    Project initiation
    37 days
    01/05/19 8:00
    20/06/19 17:00
     
    3
    Consult with Stakeholder
    14 days
    01/05/19 8:00
    20/05/19 17:00
     
    4
    Finalizing / Approving of the Project Charter
    3 days
    01/05/19 8:00
    03/05/19 17:00
     
    5
    Project Team Set-up
    10 days
    06/05/19 8:00
    17/05/19 17:00
    4
    6
    Approval for Project Initiation
    1 day
    20/05/19 8:00
    20/05/19 17:00
    5
    7
    Gather Requirements and Budget
    20 days
    21/05/19 8:00
    17/06/19 17:00
     
    8
    Preliminary Project Research
    7 days
    21/05/19 8:00
    29/05/19 17:00
    6
    9
    Data Collection & Analysis
    7 days
    21/05/19 8:00
    29/05/19 17:00
    6
    10
    Project Feasibility Assessment
    3 days
    30/05/19 8:00
    03/06/19 17:00
    8;9
    11
    Fund Planning
    7 days
    04/06/19 8:00
    12/06/19 17:00
    10
    12
    Fund Sourcing Approvals
    10 days
    04/06/19 8:00
    17/06/19 17:00
    10
    13
    Carry out cost benefit
    3 days
    18/06/19 8:00
    20/06/19 17:00
    11;12
    14
    Project planning
    16 days
    21/06/19 8:00
    12/07/19 17:00
     
    15
    Consult with project managers
    3 days
    21/06/19 8:00
    25/06/19 17:00
     
    16
    Project Method Identification
    1 day
    21/06/19 8:00
    21/06/19 17:00
    13
    17
    Project Organization, Structure, and reporting Structure Finalization
    2 days
    24/06/19 8:00
    25/06/19 17:00
    16
    18
    Identify scope
    10 days
    26/06/19 8:00
    09/07/19 17:00
     
    19
    Scope / Schedule / Budget Planning
    10 days
    26/06/19 8:00
    09/07/19 17:00
    17
    20
    Quality Planning
    10 days
    26/06/19 8:00
    09/07/19 17:00
    17
    21
    Risk Planning
    10 days
    26/06/19 8:00
    09/07/19 17:00
    17
    22
    Documentation
    10 days
    26/06/19 8:00
    09/07/19 17:00
    17
    23
    Communication plan
    3 days
    10/07/19 8:00
    12/07/19 17:00
    19;20;21;22
    24
    Project execution
    128 days
    21/06/19 8:00
    17/12/19 17:00
     
    25
    Allocating money
    3 days
    15/07/19 8:00
    17/07/19 17:00
    23
    26
    Identify resource
    30 days
    18/07/19 8:00
    28/08/19 17:00
     
    27
    Resource Planning
    3 days
    18/07/19 8:00
    22/07/19 17:00
    25
    28
    Material Resource Identification
    3 days
    23/07/19 8:00
    25/07/19 17:00
    27
    29
    Procurement Planning
    5 days
    26/07/19 8:00
    01/08/19 17:00
    28
    30
    Vendor / Supplier Negotiation
    10 days
    02/08/19 8:00
    15/08/19 17:00
    29
    31
    Contract Negotiation, Sign-off & Payments
    10 days
    02/08/19 8:00
    15/08/19 17:00
    29
    32
    Receipt of Materials
    7 days
    16/08/19 8:00
    26/08/19 17:00
    30;31
    33
    Quality Checks
    1 day
    27/08/19 8:00
    27/08/19 17:00
    32
    34
    Resource Allocation
    1 day
    28/08/19 8:00
    28/08/19 17:00
    33
    35
    Construction
    64 days
    29/08/19 8:00
    26/11/19 17:00
     
    36
    Phase 1 Construction
    30 days
    29/08/19 8:00
    09/10/19 17:00
    34
    37
    Quality Review & Approval o Phase 1 Delivery
    30 days
    29/08/19 8:00
    09/10/19 17:00
    34
    38
    Phase 2 Construction
    15 days
    10/10/19 8:00
    30/10/19 17:00
    36;37
    39
    Quality Review & Approval o Phase 2 Delivery
    15 days
    10/10/19 8:00
    30/10/19 17:00
    36;37
    40
    Phase 3 Construction
    15 days
    31/10/19 8:00
    20/11/19 17:00
    38;39
    41
    Quality Review & Approval o Phase 3 Delivery
    15 days
    31/10/19 8:00
    20/11/19 17:00
    38;39
    42
    Construction Process Closure
    3 days
    21/11/19 8:00
    25/11/19 17:00
    40;41
    43
    Review & Approvals
    1 day
    26/11/19 8:00
    26/11/19 17:00
    42
    44
    Project control
    109 days
    21/06/19 8:00
    20/11/19 17:00
     
    45
    Recruitment
    10 days
    21/06/19 8:00
    04/07/19 17:00
    13
    46
    Testing
    60 days
    29/08/19 8:00
    20/11/19 17:00
    34
    47
    Allocating responsibilities
    10 days
    05/07/19 8:00
    18/07/19 17:00
    45
    48
    Project closure
    15 days
    27/11/19...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here