Answer To: The POM+ Project* Big Kola Company has been concerned that specialized fruit drinks have been...
Varun answered on Oct 31 2021
FIle.mpp
Gantt Chart.pdf
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Unique ID Early Finish Early Start
1 POM+Project 135 days Tue 1/3/12 Fri 7/13/12 2 Fri 7/13/12 Tue 1/3/12
2 R&D product development45 days Tue 1/3/12 Wed 3/7/12 3 Wed 3/7/12 Tue 1/3/12
3 Need survey 20 days Tue 1/3/12 Wed 2/1/12 1 Wed 2/1/12 Tue 1/3/12
4 Set product
specs
15 days Wed 2/1/12 Wed
2/22/12
3 4 Wed 2/22/12 Wed 2/1/12
5 Shelf life report 10 days Wed 2/22/12Wed 3/7/12 4 8 Wed 3/7/12 Wed 2/22/12
6 Nutrition
report
5 days Wed
2/22/12
Wed
2/29/12
4 5 Wed 2/29/12 Wed 2/22/12
7 Secure fruit
suppliers
20 days Wed 3/7/12 Wed 4/4/12 5,6 6 Wed 4/4/12 Wed 3/7/12
8 Initial Production 85 days Wed 2/22/12Thu 6/21/12 7 Thu 6/21/12 Wed 2/22/12
9 Equipment rehab30 days Wed 2/22/12Wed 4/4/12 4 9 Wed 4/4/12 Wed 2/22/12
10 Production trials15 days Wed 4/4/12 Wed 4/25/127,9 10 Wed 4/25/12 Wed 4/4/12
11 Quality trials 20 days Wed 4/25/12Wed 5/23/1210 11 Wed 5/23/12 Wed 4/25/12
12 Quality metrics 5 days Wed 5/23/12Thu 5/31/12 11 38 Thu 5/31/12 Wed 5/23/12
13 Quality training 15 days Thu 5/31/12 Thu 6/21/12 12 39 Thu 6/21/12 Thu 5/31/12
14 Distribution 45 days Wed 3/7/12 Wed 5/9/12 40 Wed 5/9/12 Wed 3/7/12
15 Market testing 30 days Wed 3/7/12 Wed 4/18/125,6 41 Wed 4/18/12 Wed 3/7/12
16 Package design 15 days Wed 4/18/12Wed 5/9/12 15 42 Wed 5/9/12 Wed 4/18/12
17 Select distributors25 days Wed 3/7/12 Wed 4/11/125,6 43 Wed 4/11/12 Wed 3/7/12
18 Legal 15 days Wed 4/18/12Wed 5/9/12 44 Wed 5/9/12 Wed 4/18/12
19 Complete FDA certification15 days Wed 4/18/12Wed 5/9/12 7,15 45 Wed 5/9/12 Wed 4/18/12
20 Register trademark5 days Wed 4/18/12Wed 4/25/127,15 46 Wed 4/25/12 Wed 4/18/12
21 Prepare product launch15 days Thu 6/21/12 Fri 7/13/12 13,16,17,19FS+25 days,20FS+15 days47 Fri 7/13/12 Thu 6/21/12
22 0 days Tue 1/3/12 Tue 1/3/12 48 Tue 1/3/12 Tue 1/3/12
23 0 days Tue 1/3/12 Tue 1/3/12 49 Tue 1/3/12 Tue 1/3/12
24 0 days Tue 1/3/12 Tue 1/3/12 50 Tue 1/3/12 Tue 1/3/12
25 0 days Tue 1/3/12 Tue 1/3/12 51 Tue 1/3/12 Tue 1/3/12
26 0 days Tue 1/3/12 Tue 1/3/12 52 Tue 1/3/12 Tue 1/3/12
27 0 days Tue 1/3/12 Tue 1/3/12 53 Tue 1/3/12 Tue 1/3/12
28 0 days Tue 1/3/12 Tue 1/3/12 54 Tue 1/3/12 Tue 1/3/12
29 0 days Tue 1/3/12 Tue 1/3/12 55 Tue 1/3/12 Tue 1/3/12
30 0 days Tue 1/3/12 Tue 1/3/12 56 Tue 1/3/12 Tue 1/3/12
31 0 days Tue 1/3/12 Tue 1/3/12 57 Tue 1/3/12 Tue 1/3/12
32 0 days Tue 1/3/12 Tue 1/3/12 26 58 Tue 1/3/12 Tue 1/3/12
33 0 days Tue 1/3/12 Tue 1/3/12 59 Tue 1/3/12 Tue 1/3/12
34 0 days Tue 1/3/12 Tue 1/3/12 60 Tue 1/3/12 Tue 1/3/12
35 0 days Tue 1/3/12 Tue 1/3/12 61 Tue 1/3/12 Tue 1/3/12
36 0 days Tue 1/3/12 Tue 1/3/12 62 Tue 1/3/12 Tue 1/3/12
37 0 days Tue 1/3/12 Tue 1/3/12 63 Tue 1/3/12 Tue 1/3/12
38 0 days Tue 1/3/12 Tue 1/3/12 64 Tue 1/3/12 Tue 1/3/12
39 0 days Tue 1/3/12 Tue 1/3/12 65 Tue 1/3/12 Tue 1/3/12
40 0 days Tue 1/3/12 Tue 1/3/12 66 Tue 1/3/12 Tue 1/3/12
41 0 days Tue 1/3/12 Tue 1/3/12 12 Tue 1/3/12 Tue 1/3/12
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
J F M A M J J A S O
Half 1, 2013 Half 2, 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Slack
Student Name
#
Page 1
Project: Project1
Date: Fri 11/5/21
Gantt Chart_Resource Loaded.pdf
ID Task
Mode
Unique ID Task Name Duration Start Finish PredecessorsResource Names Early Finish Early Start Late Finish Late Start Total Slack
1 2 POM+Project 135 days Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 Tue 1/3/12 Fri 7/13/12 Tue 1/3/12 0 days
2 3 R&D product development45 days Tue 1/3/12 Wed 3/7/12 Wed 3/7/12 Tue 1/3/12 Wed 3/7/12 Tue 1/3/12 0 days
3 1 Need survey 20 days Tue 1/3/12 Wed 2/1/12 Marketing Staff[500%] Wed 2/1/12 Tue 1/3/12 Wed 2/1/12 Tue 1/3/12 0 days
4 4 Set product
specs
15 days Wed 2/1/12 Wed
2/22/12
3 Marketing Staff[200%],R&D[400%] Wed 2/22/12 Wed 2/1/12 Wed 2/22/12 Wed 2/1/12 0 days
5 8 Shelf life report 10 days Wed 2/22/12Wed 3/7/12 4 R&D[300%] Wed 3/7/12 Wed 2/22/12 Wed 3/7/12 Wed 2/22/12 0 days
6 5 Nutrition
report
5 days Wed
2/22/12
Wed
2/29/12
4 R&D[300%] Wed 2/29/12 Wed 2/22/12 Wed 3/7/12 Wed 2/29/12 5 days
7 6 Secure fruit
suppliers
20 days Wed 3/7/12 Wed 4/4/12 5,6 Purchasing Wed 4/4/12 Wed 3/7/12 Wed 4/4/12 Wed 3/7/12 0 days
8 7 Initial Production 85 days Wed 2/22/12Thu 6/21/12 Thu 6/21/12 Wed 2/22/12 Thu 6/21/12 Wed 2/22/12 0 days
9 9 Equipment rehab30 days Wed 2/22/12Wed 4/4/12 4 Engineering[1,000%],Production[2,000%] Wed 4/4/12 Wed 2/22/12 Wed 4/4/12 Wed 2/22/12 0 days
10 10 Production trials15 days Wed 4/4/12 Wed 4/25/127,9 Engineering[1,000%],Production[1,500%],PurchasingWed 4/25/12 Wed 4/4/12 Wed 4/25/12 Wed 4/4/12 0 days
11 11 Quality trials 20 days Wed 4/25/12Wed 5/23/1210 Production[500%],Quality Engineers[300%] Wed 5/23/12 Wed 4/25/12 Wed 5/23/12 Wed 4/25/12 0 days
12 38 Quality metrics 5 days Wed 5/23/12Thu 5/31/12 11 Production,Quality Engineers[300%] Thu 5/31/12 Wed 5/23/12 Thu 5/31/12 Wed 5/23/12 0 days
13 39 Quality training 15 days Thu 5/31/12 Thu 6/21/12 12 Production[1,500%],Quality Engineers[300%] Thu 6/21/12 Thu 5/31/12 Thu 6/21/12 Thu 5/31/12 0 days
14 40 Distribution 45 days Wed 3/7/12 Wed 5/9/12 Wed 5/9/12 Wed 3/7/12 Thu 6/21/12 Wed 3/14/12 5 days
15 41 Market testing 30 days Wed 3/7/12 Wed 4/18/125,6 Marketing Staff[500%] Wed 4/18/12 Wed 3/7/12 Wed 4/25/12 Wed 3/14/12 5 days
16 42 Package design 15 days Wed 4/18/12Wed 5/9/12 15 Designers[300%],Marketing Staff Wed 5/9/12 Wed 4/18/12 Thu 6/21/12 Thu 5/31/12 30 days
17 43 Select distributors25 days Wed 3/7/12 Wed 4/11/125,6 Marketing Staff[500%] Wed 4/11/12 Wed 3/7/12 Thu 6/21/12 Wed 5/16/12 50 days
18 44 Legal 15 days Wed 4/18/12Wed 5/9/12 Wed 5/9/12 Wed 4/18/12 Thu 5/31/12 Wed 4/25/12 5 days
19 45 Complete FDA certification15 days Wed 4/18/12Wed 5/9/12 7,15Legal Staff[300%] Wed 5/9/12 Wed 4/18/12 Wed 5/16/12 Wed 4/25/12 5 days
20 46 Register trademark5 days Wed 4/18/12Wed 4/25/127,15Legal Staff[300%] Wed 4/25/12 Wed 4/18/12 Thu 5/31/12 Wed 5/23/12 25 days
21 47 Prepare product launch15 days Thu 6/21/12 Fri 7/13/12 13,16,17,19FS+25 days,20FS+15 daysQuality Engineers[300%],Purchasing[200%],Production[1,500%],Marketing Staff[500%],Engineering[500%],R&DFri 7/13/12 Thu 6/21/12 Fri 7/13/12 Thu 6/21/12 0 days
22 48 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
23 49 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
24 50 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
25 51 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
26 52 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
27 53 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
28 54 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
29 55 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
30 56 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
31 57 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
32 58 0 days Tue 1/3/12 Tue 1/3/12 26 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
33 59 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
34 60 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
35 61 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
36 62 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
37 63 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
38 64 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
39 65 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
40 66 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
41 12 0 days Tue 1/3/12 Tue 1/3/12 Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
Marketing Staff[500%]
Marketing Staff[200%],R&D[400%]
R&D[300%]
R&D[300%]
Purchasing
Engineering[1,000%],Production[2,000%]
Engineering[1,000%],Production[1,500%],Purchasing
Production[500%],Quality Engineers[300%]
Production[1,500%],Quality Engineers[300%]
Marketing Staff[500%]
Designers[300%],Marketing Staff
Marketing Staff[500%]
Legal Staff[300%]
Legal Staff[300%]
Quality Engineers[300%],Purchasing[200%],Production[1,500%],Marketing Staff[500%],Engineering[500%],R&D
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
J F M A M J J
Half 1, 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Slack
Student Name
#
Page 1
Project: Project1
Date: Fri 11/5/21
ID Task
Mode
Unique ID Task Name Duration Start Finish PredecessorsResource Names Early Finish Early Start Late Finish Late Start Total Slack
42 37 0 days Tue 1/3/12 Tue 1/3/12 Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
43 13 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
44 14 0 days Tue 1/3/12 Tue 1/3/12 43 Engineering,Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
45 15 0 days Tue 1/3/12 Tue 1/3/12 Engineering,Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
46 16 0 days Tue 1/3/12 Tue 1/3/12 Engineering,Purchasing,R&D Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
47 17 0 days Tue 1/3/12 Tue 1/3/12 R&D Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
48 18 0 days Tue 1/3/12 Tue 1/3/12 Engineering,R&D Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
49 19 0 days Tue 1/3/12 Tue 1/3/12 Engineering,R&D Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
50 20 0 days Tue 1/3/12 Tue 1/3/12 Marketing Staff,Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
51 21 0 days Tue 1/3/12 Tue 1/3/12 Marketing Staff,Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
52 22 0 days Tue 1/3/12 Tue 1/3/12 Purchasing,Marketing Staff Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
53 36 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
54 35 0 days Tue 1/3/12 Tue 1/3/12 Engineering,Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
55 31 0 days Tue 1/3/12 Tue 1/3/12 Engineering,Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
56 32 0 days Tue 1/3/12 Tue 1/3/12 Engineering,Purchasing,R&D Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
57 33 0 days Tue 1/3/12 Tue 1/3/12 R&D Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
58 34 0 days Tue 1/3/12 Tue 1/3/12 Engineering,R&D Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
59 29 0 days Tue 1/3/12 Tue 1/3/12 Engineering,R&D Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
60 30 0 days Tue 1/3/12 Tue 1/3/12 Marketing Staff,Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
61 28 0 days Tue 1/3/12 Tue 1/3/12 Marketing Staff,Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
62 27 0 days Tue 1/3/12 Tue 1/3/12 Purchasing,Marketing Staff Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
63 24 0 days Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
64 23 0 days Tue 1/3/12 Tue 1/3/12 Marketing Staff Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
65 25 0 days Tue 1/3/12 Tue 1/3/12 Marketing Staff Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
66 26 0 days Tue 1/3/12 Tue 1/3/12 Engineering,Purchasing Tue 1/3/12 Tue 1/3/12 Fri 7/13/12 Fri 7/13/12 135 days
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
January 3, 2012
J F M A M J J
Half 1, 2013
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Slack
Student Name
#
Page 2
Project: Project1
Date: Fri 11/5/21
Gantt Chart_Resource Loaded_4A.pdf
ID Task
Mode
Unique ID Task Name Duration Start Finish PredecessorsResource Names Early Finish Early Start Late Finish Late Start Total Slack Cost
1 2 POM+Project 145 days Tue 1/3/12 Fri 7/27/12 Fri 7/27/12 Tue 1/3/12 Fri 7/27/12 Tue 1/3/12 0 days $1,085,440.00
2 3 R&D product development50 days Tue 1/3/12 Wed 3/14/12 Wed 3/14/12 Tue 1/3/12 Wed 3/21/12 Tue 1/3/12 0 days $131,840.00
3 1 Need survey 22 days Tue 1/3/12 Fri 2/3/12 Marketing Staff[500%] Fri 2/3/12 Tue 1/3/12 Fri 2/3/12 Tue 1/3/12 0 days $70,400.00
4 4 Set product
specs
18 days Fri 2/3/12 Wed
2/29/12
3 Marketing Staff[200%],R&D[400%] Wed 2/29/12 Fri 2/3/12 Wed 2/29/12 Fri 2/3/12 0 days $32,640.00
5 8 Shelf life report 10 days Wed 2/29/12Wed 3/14/124 R&D[300%] Wed 3/14/12 Wed 2/29/12 Wed 3/21/12 Wed 3/7/12 5 days $19,200.00
6 5 Nutrition
report
5 days Wed
2/29/12
Wed 3/7/12 4 R&D[300%] Wed 3/7/12 Wed 2/29/12 Wed 3/21/12 Wed 3/14/12 10 days $9,600.00
7 6 Secure fruit
suppliers
20 days Wed
3/14/12
Wed
4/11/12
5,6 Purchasing Wed 4/11/12 Wed 3/14/12 Wed 4/18/12 Wed 3/21/12 5 days $9,600.00
8 7 Initial Production 90 days Wed 2/29/12Fri 7/6/12 Fri 7/6/12 Wed 2/29/12 Fri 7/6/12 Wed 2/29/12 0 days $410,400.00
9 9 Equipment rehab35 days Wed 2/29/12Wed 4/18/124 Engineering[1,000%],Production[2,000%] Wed 4/18/12 Wed 2/29/12 Wed 4/18/12 Wed 2/29/12 0 days $294,400.00
10 10 Production trials15 days Wed 4/18/12Wed 5/9/12 7,9 Engineering[1,000%],Production[1,500%],PurchasingWed 5/9/12 Wed 4/18/12 Wed 5/9/12 Wed 4/18/12 0 days $26,400.00
11 11 Quality trials 20 days Wed 5/9/12 Thu 6/7/12 10 Production[500%],Quality Engineers[300%] Thu 6/7/12 Wed 5/9/12 Thu 6/7/12 Wed 5/9/12 0 days $48,000.00
12 38 Quality metrics 5 days Thu 6/7/12 Thu 6/14/12 11 Production,Quality Engineers[300%] Thu 6/14/12 Thu 6/7/12 Thu 6/14/12 Thu 6/7/12 0 days $5,600.00
13 39 Quality training 15 days Thu 6/14/12 Fri 7/6/12 12 Production[1,500%],Quality Engineers[300%] Fri 7/6/12 Thu 6/14/12 Fri 7/6/12 Thu 6/14/12 0 days $36,000.00
14 40 Distribution 45 days Wed 3/14/12Wed 5/16/12 Wed 5/16/12 Wed 3/14/12 Fri 7/6/12 Wed 3/28/12 10 days $207,200.00
15 41 Market testing 30 days Wed 3/14/12Wed 4/25/125,6 Marketing Staff[500%] Wed 4/25/12 Wed 3/14/12 Wed 5/9/12 Wed 3/28/12 10 days $96,000.00
16 42 Package design 15 days Wed 4/25/12Wed 5/16/1215 Designers[300%],Marketing Staff Wed 5/16/12 Wed 4/25/12 Fri 7/6/12 Thu 6/14/12 35 days $31,200.00
17 43 Select distributors25 days Wed 3/14/12Wed 4/18/125,6 Marketing Staff[500%] Wed 4/18/12 Wed 3/14/12 Fri 7/6/12 Thu 5/31/12 55 days $80,000.00
18 44 Legal 15 days Wed 4/25/12Wed 5/16/12 Wed 5/16/12 Wed 4/25/12 Thu 6/14/12 Wed 5/9/12 10 days $57,600.00
19 45 Complete FDA certification15 days Wed 4/25/12Wed 5/16/127,15Legal Staff[300%] Wed 5/16/12 Wed 4/25/12 Thu 5/31/12 Wed 5/9/12 10 days $43,200.00
20 46 Register trademark5 days Wed 4/25/12Wed 5/2/12 7,15Legal Staff[300%] Wed 5/2/12 Wed...