13-13 Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 3 5 7 B 2.5 3.5 5 C 5 7 9 D 5 6 9 E 5...

1 answer below »


Suppose that the following estimates of activity times (in weeks) were provided for the network shown below:






























































Activity





Optimistic





Most Probable





Pessimistic




A




3




5




7




B




2.5




3.5




5




C




5




7




9




D




5




6




9




E




5




7




10




F




2




3.5




5




G




9




11




14




H




5




7




12




What is the probability that the project will be completed. If required, round your answers to four decimal places





13-13 Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 3 5 7 B 2.5 3.5 5 C 5 7 9 D 5 6 9 E 5 7 10 F 2 3.5 5 G 9 11 14 H 5 7 12 What is the probability that the project will be completed. If required, round your answers to four decimal places. 0. Within 20 weeks? 0. Within 22.5 weeks? 0. Within 24 weeks?

Answered Same DayNov 07, 2019

Answer To: 13-13 Suppose that the following estimates of activity times (in weeks) were provided for the...

David answered on Nov 30 2019
127 Votes
13-13
Suppose that the following estimates of activity times (in weeks) were provided for the netwo
rk shown below:
    Activity
    Optimistic
    Most...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here