https://mediaplayer.pearsoncmg.com/assets/_embed.true/Xk8i4DoLkQaFxl_NCo2U6DkIX4fvQ25P Build your own PERT chart for a real-world project or project of interest to you. Estimate times when you don't...

1 answer below »


https://mediaplayer.pearsoncmg.com/assets/_embed.true/Xk8i4DoLkQaFxl_NCo2U6DkIX4fvQ25P
Build your own PERT chart for a real-world project or project of interest to you. Estimate times when you don't know them. Find the critical path. Discuss.
Answered 1 days AfterNov 08, 2021

Answer To: https://mediaplayer.pearsoncmg.com/assets/_embed.true/Xk8i4DoLkQaFxl_NCo2U6DkIX4fvQ25P Build your...

Sudipa answered on Nov 09 2021
114 Votes
Name of Student : :
# : :
1.Describe your project and clearly state your goals for the project.
2.Create a Microsoft Project File for your project and
name it appropriately including your full nameProject goal statement : Project intends to complete the plastering of ceiling of a building having two sections of 150 X 165 square meters at 15 meters height
FMPP file attached for reference.
Project name : Building Plastering_Full Name
3. Choose a Start or Finish date for your project. Decide if you will Schedule from Project Start Date or Schedule from Project Finish Date. Make sure your choices are in line with your Project Goal.
Start Date for Project Scheduling has been chosen. Start Date shall be 03rd October 2021.
4.You might want to start on paper. Develop a series of tasks and sub-tasks for this project. There should be no fewer than twelve tasks with specific durations (not including Summary Tasks and milestones for example). Think about reasonable durations for your tasks. Tasks should make logical sense. Put these tasks into your project file in the correct order. Try to group them appropriately using a clear Work Breakdown Structure. Think about what kinds of dependencies you will need to link tasks with?
    S.No,
    Task Name
    Duration
    Predecessors
    3
     Site Visit and Area Reconfirmation
    4 days
     
    4
     Finalization of Contractor
    7 days
    3
    6
     Mobilization of Contractor & labor
    0 days
    4
    7
     Ordering of Scaffolding members & platforms for Height Works
    2 days
    6FS-1 day
    8
     Ordering of Cement
    1 day
    6SS-1 day
    9
     Ordering of Sand
    1 day
    6SS-1 day
    10
     Ordering of Dust
    1 day
    6SS-1 day
    12
     Daily Safety Meet
    20 days
     
    41
     Delivery of Sand, Dust and Cement
    3 days
    8FS+1 day,9FS+1 day,10FS+1...
SOLUTION.PDF