Complete this exercise in MSProject. Submit both your MSProject file and your answers to the questions below. You can use your solution to the scheduling exercise (before any tasks were crashed) as the basis for this exercise.
Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource assignments are as shown:
Task
Predecessor
Duration
A
-
2
HR Manager
B
7
HR Analyst
C
4
D
B, C
8
E
Benefits Coordinator
F
6
G
3
H
E, F