Complete this exercise in MSProject. Submit both your MSProject file and your answers to the questions below. You can use your solution to the scheduling exercise (before any tasks were crashed) as...

1 answer below »






Complete this exercise in MSProject. Submit both your MSProject file and your answers to the questions below. You can use your solution to the scheduling exercise (before any tasks were crashed) as the basis for this exercise.












Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource assignments are as shown:




























































































































































































Task

















Predecessor

















Duration














Resource








A







-







2







HR Manager







B







-







7







HR Analyst







C







A







4







HR Analyst







D







B, C







8







HR Analyst







E







D







8







Benefits Coordinator







F







D







6







Benefits Coordinator







G







E







3







HR Analyst







H







E, F







6







HR Manager













  1. Before adding resources, the project takes 29 days. Once resources constraints are entered and leveled, what is the total number of days to complete the project?








  2. According to the project statistics, what is the planned cost of the project after you have leveled resources in Q1?








  3. If the HR Manager is only available to work on the project 50% of the time, rather than dedicated to the project full-time, how many days will it take to complete the project? Make sure that you have again leveled the resources





Answered 1 days AfterFeb 09, 2023

Answer To: Complete this exercise in MSProject. Submit both your MSProject file and your answers to the...

Banasree answered on Feb 11 2023
35 Votes
1.Ans. – Before adding resources, it was 29 days. However, after resources constraints are entered and levelled the total number of days to complete the project was 20 days.
2. Ans. – Refer to the project statistic, the planned cost of the project after levelled resources was - $1170.00
3. Ans....