ExerciseComplete this exercise in MSProject. You can use your solution to the resources exercise (with the HR Manager available at 100%) as the basis for this exercise.Your project began on June 1 and...

1 answer below »









Exercise
































































































































































Task









Elapsed Days of Work








Days of Work Remaining






A







2







0







B







8







0







C







4







0







D







10







4







E







0







8







F







0







6







G







0







3







H







0







6








Update the MSProject plan to reflect the progress and submit your file along with answers to the following questions:








  1. What is the planned cost of completing the project?




  2. What is the schedule variance as of July 1?






  3. What is the CPI as of July 1?





" style="display: block; overflow-wrap: break-word; overflow: auto hidden;">


Complete this exercise in MSProject. You can use your solution to the resources exercise (with the HR Manager available at 100%) as the basis for this exercise.



Your project began on June 1 and it is now July 1. The progress and remaining time on each task is as follows:






















































Task





Elapsed Days of Work






Days of Work Remaining




A



2



0



B



8



0



C



4



0



D



10



4



E



0



8



F



0



6



G



0



3



H



0



6




Update the MSProject plan to reflect the progress and submit your file along with answers to the following questions:




  1. What is the planned cost of completing the project?


  2. What is the schedule variance as of July 1?




  3. What is the CPI as of July 1?















Answered Same DayFeb 18, 2023

Answer To: ExerciseComplete this exercise in MSProject. You can use your solution to the resources exercise...

Banasree answered on Feb 19 2023
34 Votes
1.Ans.
Assuming that the cost per day for each task is $100, the planned cost of completing the pro
ject would be:
Planned Cost = (Elapsed Days of Work + Days of Work Remaining) x Cost per Day
For each task, the planned cost would be:
Task A: (2 + 0) x $100 = $200
Task B: (8 + 0) x $100 = $800
Task C: (4 + 0) x $100 = $400
Task D: (10 + 4) x $100 = $1400
Task E: (0 + 8) x $100 = $800
Task F: (0 + 6) x $100 = $600
Task G: (0 + 3) x $100 = $300
Task H: (0 + 6) x $100 = $600
Therefore, the planned cost of completing the project would be:
Planned Cost = $200 + $800 + $400 + $1400 + $800 + $600 + $300 + $600
= $4,100
The planned cost of completing the project is $4,100.
2.Ans.
The schedule variance as of July 1 would be:
SV = sum of (planned duration - actual duration) up to July 1
SV = (3 - 2) + (10 -...