Risk Register Assignment;In this assignment you are to prepare a complete risk register utilizing the scenario and instructions provided.You are the project manager assigned to a project to...

1 answer below »









Risk Register Assignment;In this assignment you are to prepare a complete risk register utilizing the scenario and instructions provided.












You are the project manager assigned to a project to upgrade an old bus shelter. The shelter is












located along South Street traveling eastbound. South Street is a dual highway with a speed












restriction of 45 miles an hour. There are three eastbound lanes and a concrete sidewalk. The












bus shelter is set back from the roadway approximately 5 feet. To the rear of the bus shelter is a












cul-de-sac surrounded by residential dwellings and a brick wall in close proximity to the bus












shelter. The enclosed photos are provided to you as a resource to be used in completing the












assignment.












Your supervisor discusses the project with you and requests that you develop a risk register












associated with this project before work begins. You will need to identify potential risks












including threats and opportunities, and develop a Risk Register in Microsoft Excel (.xls) format.












Your assignment, is to design and present a complete risk register associated with the scenario












provided. Your risk register should include the following items:












Risk Identification





– You are to identify and list at least five potential risks associated with this













project. This list should include at least one opportunity risk. Each risk is to be clearly described












so that it can be easily understood and relatable to the project.












Risk Category





– Determine and list the corresponding category associated with each risk. For













example, is the risk you identified associated with schedule, scope, budget, etc.












Likelihood/Probability





– Estimate and list the likelihood of each risk occurring. You must













identify and explain the scale selected. For example, you can use a high, medium, and low scale,












however, this scale must equate to numerical values to provide for effective risk score












calculation – i. e. High = 10








lmpact




– Estimate and list the impact on the project of each risk should it occur. You must












identify and explain the scale selected. You may select either a qualitative or quantitative scale.












Rank –





For each risk, calculate and list a Risk Score (i.e. Probability and Impact Score) which













will enable you to rank and prioritize each risk. Then be sure each risk is assigned a priority












number. You are not required to re-order your risks on the Risk Register.












Root Cause





– For each risk, list at least one potential root cause that may be the true reason













behind the risk being present. There should be one root cause associated with each risk. Each












root cause must be clearly described and be understandable. For example, “poor planning” is not












an acceptable root cause. You should also identify and briefly describe one root cause analysis












technique you would use to assist in this discovery.












Risk Response Strategy





– For each risk, create at least one response strategy to be used to













address the risk should it occur. Your risk response should be clear and understandable. You












should also identify and include the category of your risk response, i.e. Avoidance, Mitigation,












etc.








Risk Response Cost





– For each risk response, provide an estimated cost, to implement the













strategy.












Risk Owner





– For each risk list who will be the owner of the risk. You may create fictitious













names and titles that can be used to complete this portion of the risk register.












Risk Status





– List a hypothetical status for each risk. The status should be clear and













understandable.












Other Fields





– Identify at least one field you as the project manager would add to your Risk













Register that may be needed for this specific project, or one that you believe will be helpful to












your project team.









Answered Same DayMar 07, 2023

Answer To: Risk Register Assignment;In this assignment you are to prepare a complete risk register utilizing...

Asif answered on Mar 08 2023
33 Votes
Risk Register for Bus Shelter
    Risk Identification        Risk Category        Likelihood/Probability            Impact    
Rank    Root Cause        Risk Response Strategy            Risk Response Cost        Risk Owner        Risk Status    Other Fields
    Inclement weather during construction        External        High            Moderate    6    Unpredictable weather patterns        Mitigate by closely monitoring weather reports and planning for possible delays in construction schedule            $5,000        Construction Manager        Active    Communication Plan
    Unsuitable site conditions        Internal        Low            Moderate    10    Poor...