The deadline for your mid-module assignment is at the end of unit 4.The board of directors of Lightning Fast have become increasingly concerned about the theme park’s decline in sales and...

1 answer below »



The deadline for your mid-module assignment is at the end of unit 4.


The board of directors of Lightning Fast have become increasingly concerned about the theme park’s decline in sales and profitability over the last 6 months. The company have hired your services as a project management consultant to undertake detailed analysis of its current business activities and its software systems to enable it to overcome these difficulties and restore the confidence of its key stakeholders.




This assignment requires you to produce a report (1500 – 2000 words) encompassing the following:




Part A (1500 words):







  1. Analysis of visitors to the theme park has revealed that 90% are UK based whilst only 10% are foreign tourists. Identify 2 projects e.g. a new ride, developing a hotel complex etc. which would make the park more attractive to foreign tourists.



  2. Justify why these projects are suitable and explain they will create business “value” for Lightning Fast and will allow it to boost its sales and profitability.



  3. Based upon your findings select of one of the projects you have discussed and explain to the board of directors why they should proceed to develop it with immediate effect.



  4. Estimate the RBS (Requirements Breakdown Structure) for your selected project.



  5. Consider the 4 quadrants of the Project Landscape and briefly explain which quadrant your project lies within.



  6. Explore how the project will allow the company to restore the confidence of its key internal and external stakeholders. Remember to support with reputable wider reading and reference this in full.



  7. You may wish to undertake PESTLE, Porter’s 5 forces, SWOT and stakeholder analyses to increase your knowledge and understanding of the subject matter being investigated. If this is the case – these supporting materials should be placed in the appendices and referred to within the main body of your report.






Part B (500 words):







  1. Lightning Fast currently usesProject Libreto develop, manage and control its projects. However, its project managers are becoming increasingly dissatisfied with its facilities. You are required to download this software and enter the precedence table shown below.



  2. You are required to briefly appraise Project Libre's features, advantages and limitations.



  3. Identify two alternative project management software systems which could replace Project Libre and evaluate their features, advantages and limitations.



  4. Based upon your analysis select one of the “two alternatives” and recommend to the board of directors which one they should buy. Explain the rationale for your choice.



  5. Finally, produce a conclusion to critique Part A and Part B.






Assignment Precedence Table for Part B:


















































































































































































Task






Duration (Weeks)






Precedence






Resources



A2N/A2
B2A1
C3A2
D6B3
E3C2
F14A6
G4E3
H8D,F,G5



Please note,both Part A and Part B are requiredto complete the assignment.




Submission Requirements











  • Word processed report which fulfils the Parts A and B.



  • The Project Libre file which contains the Assignment Precedence Table - save this file under an appropriate name. For example, "Project".










The learning outcomes for this assignment are:










  • Develop the unique criteria that an individual project would be measured againstknown benchmarks.



  • Apply understanding of project management concepts and software to define,implement, and modify projects.















































Answered 1 days AfterJun 29, 2023

Answer To: The deadline for your mid-module assignment is at the end of unit 4.The board of directors of...

Shubham answered on Jun 30 2023
22 Votes
SOLUTION.PDF

Answer To This Question Is Available To Download