This case study is on Scope Management.(Source: Boeing's Virtual Fence case in Project Management Achieving Competitive Advantage by Jeffery Pinto (4th Edition), Pearson Press.With...

1 answer below »





















This case study is on Scope Management.




(Source: Boeing's Virtual Fence case in Project Management Achieving Competitive Advantage by Jeffery Pinto (4th Edition), Pearson Press.




With permission from Author).




Using the concepts covered so far, identify the core issues addressed in this case, and answer the following questions:




1. What problems do you see emerging from a project such as SBInet where the government allows the contractor to determine the scope, manage all contractor relations, and decide how to share project status information with oversight bodies?




2. Consider the following two arguments: "The failure of SBInet was due to poor scope management" versus "SBINet failed because of poor oversight and project controls". Take one side or the other in this argument and justify your response.




Submit a case report addressing the two questions. The rubrics are given below.Please use the rubrics as a guide while writing the case report. You are expected to write a case report with an Introduction, Facts from the case, Analysis of the facts, Answer the 2 questions, and Conclusions. Examine all possible reasons for failure of this project. Before writing the report, perform a google search on what happened during and after this case. There are regulations that were passed by the U.S. Congress. Do some research, read the case, analyze other external


facts, and


then start writing,


























































Answered 2 days AfterApr 04, 2023

Answer To: This case study is on Scope Management.(Source: Boeing's Virtual Fence case in Project...

Dipali answered on Apr 07 2023
31 Votes
WRITTEN ASSIGNMENT        2
WRITTEN ASSIGNMENT
Table of contents
Introduction    3
Facts from the case    4
Analysis of the facts    6
Problems emerging from a project such as SBInet    9
Arguments    10
Conclusion    13
References    17
Introduction
The Secure Border Initiative (SBInet), also known as the Boeing Virtual Fence project, was an initiative started by U.S. Customs and Border Protection (CBP) to create a complete border security system. The project's goal was to combine several technologies, such as ground sensors, radar, and cameras, to build a virtual fence that would aid in securing the U.S.-Mexico border. 2009 was the projected completion date for the $1.1 billion project. When Boeing was given the project's contract in 2006, they were in charge of deciding its scope, handling all contractor interactions, and communicating project progress data to oversight a
uthorities. However, the project encountered a number of difficulties, including technical difficulties with the surveillance technologies, delays in the construction process, and cost overruns. These difficulties caused a number of delays, and the project was ultimately abandoned in 2011 after the government had invested $1 billion in it.
Many elements, such as poor scope management, oversight, and project controls, among others, contributed to the collapse of the Virtual Fence project. The contractor can be more concerned with upholding their contractual commitments than with accomplishing the goals of the project. Furthermore, the contractor could put their interests above those of the government, resulting in subpar work, delays, and cost overruns. Boeing was in charge of deciding the project's scope in the instance of the Virtual Fence, which led to a number of technical problems with the surveillance technology. The fact that Boeing oversaw all contractor relationships may have prevented collaboration and communication, adding to the project's difficulties.
The failure of the Virtual Fence project serves as a reminder of the significance of efficient scope management and cooperation between the government and the contractor. To make sure the project is in line with its goals and yields the desired results, the government must actively participate in overseeing it. To manage project risks, costs, and schedule, effective project controls are also essential. Following the Virtual Fence project's cancellation, the US Congress passed a number of laws to strengthen border security. Effective project management procedures, enhanced transparency in project reporting, and improved cooperation between government departments and contractors were all emphasized by these regulations. These rules were designed to ensure that upcoming border security initiatives are carried out successfully and effectively, achieving the desired results on schedule and under budget. Therefore, the Virtual Fence project case should serve as a warning to both contractors and government organizations. The success of a project depends on effective scope management, teamwork, and project controls, and failure to use these strategies can result in resource waste and project failure. Future projects can be carried out more skillfully, achieving the desired results and enhancing border security for the United States by learning from the mistakes of the Virtual Fence project and applying those lessons to other endeavors.
Facts from the case
The Secure Border Initiative (SBInet), also known as the Boeing Virtual Fence project, sought to use cutting-edge technology to build a virtual barrier along the US-Mexico border in order to detect and deter illegal immigration, drug trafficking, and other border crimes. The Department of Homeland Security (DHS) launched the initiative in 2006, and Boeing was chosen as the main contractor. The project's initial budget was $2.5 billion, and a three-year schedule was assigned to it (Piras et al., 2021). The objective of the project was to construct a system of observation towers, cameras, and other sensors along the border to monitor activity. In order for agents to assess and address any threats, the information gathered from these sensors was subsequently relayed to a central command centre. 6,000 miles of the US-Mexico border were supposed to be covered by the project. Yet, there were various issues with the project right away. The initial contract did not clearly define the scope of work, and as the project moved forward, the scope continued to alter. The DHS made new demands on the project without providing extra cash, and the adjustments were frequently motivated by political pressure (Han, Wang & Zhang, 2022).
Poor communication between Boeing and the DHS was a further problem. The DHS lacked a thorough understanding of the technologies utilized in the project, and Boeing failed to give the DHS enough updates on its status. Confusion and mistrust resulted from the DHS's lack of clarity regarding the types of data being gathered and how they were being used. The project encountered technical issues as well. The software utilized to evaluate the data was unable to produce useful insights, and the surveillance hardware was unable to function in the challenging border environment. The project also experienced issues with improper component integration, which resulted in inefficiencies and false alarms. In the end, the initiative was shelved in 2011, when DHS determined that it was failing to achieve its goals. The government had already spent over $1 billion on the project, and the DHS decided it was not worthwhile to continue.
Boeing and the DHS felt significant repercussions from the Virtual Fence project’s failure. Boeing, including a $500 million charge for the project’s cancellation, incurred significant financial losses. Congress opened a probe over the project's failure, and the DHS came under fire for it. The government struggled to identify a viable substitute for the Virtual Fence because of the project's failure, which also had wider ramifications for border security. Because of the project's failure, the DHS adjusted its purchase procedure. The DHS now demands a more thorough statement of work, an extensive risk management strategy, and a more reliable framework for performance measurement. Additionally, the DHS mandates more regular interactions with contractors and a deeper comprehension of the technologies utilised in projects.
The Virtual Fence project, as a whole, was a public failure that underlined the significance of efficient scope management, communication, and project control. The project's failure also brought to light the necessity of distinct project goals, an extensive risk management strategy, and a specific scope of work. Failure of the project had enormous negative effects on Boeing and the DHS's finances and political standing, as well as wider border security concerns.
Analysis of the facts
Many difficulties were encountered by the Secure Border Initiative (SBInet), often known as the Virtual Fence project, which ultimately caused it to collapse. Using a variety of technology, such as cameras, radar, and ground sensors, the project attempted to develop an extensive border security system. After winning the contract for the project, Boeing was in charge of deciding its scope, handling all contractor interactions, and informing the project's oversight committees of its progress. Unfortunately, ineffective scope management, a lack of cooperation and project controls, technical difficulties, a delay in the construction process, and cost overruns all played a part in the project's collapse (Almasifar et al., 2021).
Poor scope management was one of the main problems with the Virtual Fence project. The contractor, Boeing, decided the project scope and this might have resulted in a number of technical problems with the surveillance technologies (Quang-Huy, 2021). Boeing may have placed its interests above those of the government, which resulted in a project scope that was insufficient and didn't satisfy its requirements. Any project's success depends on effective scope management, and the government must take a proactive part in making sure the project is in line with their interests and meets their demands.
Poor oversight and project controls were a serious problem with the Virtual Fence project. The government delegated control of all contractor interactions to Boeing, who also chose how to update oversight organizations about the progress of the project. A lack of collaboration and communication between the government and the contractor because of this lack of project oversight and controls may have resulted in subpar work, delays, and cost overruns...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here